Triton shares gain on Mozambique graphite DFS

15th December 2017

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

JOHANNESBURG (miningweekly.com) – Australian company Triton Minerals is gearing up to start early construction work at its Ancuabe graphite project in Mozambique in May next year, after a definitive feasibility study (DFS) boosted its confidence in building a mine to supply the premium end of the graphite market.

The DFS determined that Ancuabe would require preproduction capital of $99.4-million to build a mine that is capable of producing about 60 000 t/y of graphite concentrate.

Triton said the DFS displayed robust economics, highlighted by average yearly revenue of $82.6-million and earnings before interest, taxes, depreciation and armortisation margins averaging 53% over a 27-year evaluation period.

The study estimates a pretax net present value of $298-million, a pretax internal rate of return 36.8% and near-term payback of 3.8 years.

“Ancuabe has market leading large/jumbo flake size distribution combined with high purity levels across all flake sizes making it suitable for both the lithium ion battery market and expandable graphite, where demand is being driven by flame retardant building materials. Our project will be based on simple mechanical flotation methods, avoiding the environmentally challenging acid purification treatments currently being used in China, which is the world’s largest producer of natural flake graphite,” Triton MD Peter Canterbury said.

The positive DFS allows Triton to focus on finalising offtake agreements, financing agreements, local approvals and early works engineering and procurement to enable a final investment decision in the first half of next year.

Early work on the site is expected to start in May and will mainly be focused on establishing the construction camp, raw water dam construction and plant site preparations.

A ten-month construction period is expected to start in August, subject to a final investment decision, government approval and financing.

The company also said that it would shift its project execution strategy to a project management contractor model, representing Triton and potentially a Chinese engineering, procurement and construction model, rather than a previously contemplated engineering, procurement and construction management model.

The DFS has been used as the basis from which to estimate an ore reserve of 24.9-million tonnes at 6.2% total graphitic content, for 1.5-million tonnes of contained graphite, at the Ancuabe T12 and T16 deposits.

Shares in Triton gained 12.5% on the ASX to trade at 8.1c a share in the late afternoon.

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION