Tala Hamza gets new price tag

29th August 2018

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – A revised feasibility study into the Tala Hamza zinc/lead project, in Algeria, has shown that the project could recover some 129 300 t/y of zinc concentrate and 26 000 t/y of lead concentrate over a mine life of 21 years.

ASX-listed Terramin Australia on Wednesday reported that a preproduction capital investment of A$449-million would be required, with the project’s post tax net present value estimated at A$399-million and its internal rate of return at 14%, based on a zinc price of $1.25/lb and a lead price of $1.05/lb.

The updated feasibility study was based on a mineral resource of 53-million tonnes a year, which includes an indicated mineral resource of 44.2-million tonnes.

The updated study compared with the original 2019 definitive feasibility study (DFS), which estimated a capital cost of $579-million to develop a four-million-tonne-a-year operation with a mine life of 12 years, producing some 310 000 t/y of zinc concentrate and 60 000 t/y of lead concentrate containing 164 000 t/y of zinc and 36 000 t/y of lead.

“Terramin is excited to be able to release the details of the Tala Hamza revised definitive feasibility study. The result is the outcome of steady and patient negotiations with our joint venture partners. It was important to engage and work consistently with our counterparts to ensure a robust long-life project that will be a flagship project in Algeria,” said Terramin CEO Richard Taylor.

“Location is everything with Tala Hamza, proximity to deep water ports, well developed infrastructure, cheap and reliable energy and an educated workforce makes this a potential world-class project,” he said.

“Getting the base case project at Tala Hamza permitted opens up optionality for expansion and exploration both within the existing area and further afield in a highly prospective emerging mining country which is looking to diversify from oil and gas.”

Based on the positive results from the DFS, and the expansion potential at Tala Hamza, Terramin is now progressing further optimisation studies and permitting in the 2018 calendar year. This was expected to allow the base case project to proceed in conjunction with studies into expansion cases.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION