BHP, Rio to invest $3bn in Escondida seawater desalination plant
PERTH (miningweekly.com) – Mining majors BHP Billiton and Rio Tinto will jointly invest $3-billion into a new 2 500 l/s seawater desalination facility for the Escondida copper mine, in Chile.
The Rio board has approved a $1.03-billion budget for its 30% interest in the project, while BHP will provide the remaining $1.97-billion.
The miners said on Friday that the desalination project would provide a sustainable supply of water for the organic growth project at the copper concentrator, which was approved in 2012, while limiting the project’s reliance on the region’s aquifers.
Construction of the new plant will start this month and will include the development of two pipelines, four high-pressure pump stations, a reservoir at the mine site and high-voltage infrastructure to support the system.
The new facility will be commissioned in 2017.
“Securing a sustainable water supply in the Atacama Desert is a major priority for all Chilean copper producers, so the approval of the Escondida water supply project is a significant milestone for our business,” BHP’s copper president Peter Beaven said on Friday.
“The new desalination facility will reduce our reliance on the region’s aquifers, which will help us to meet our environmental commitments and enable us to achieve our long-term business strategy.”
The desalination plant forms part of the organic growth project 1 (OGP1), which is aimed at replacing the Los Colorados concentrator with a new 152 000 t/d plant, and allowing access to higher-grade ore located underneath the existing facilities.
Construction of OGP1 started in February last year and commissioning is expected in the first half of 2015, increasing production to 1.3-million tonnes a year. The project will cost $3.8-billion and create up to 7 000 jobs during the construction phase.
The Escondida project is 57.5% held by BHP and 30% by Rio, while a 10% interest is held by the Jeco Corporation and the remaining 2.5% by Jeco 2.
Comments
The
functionality
you are trying to access is only available to subscribers.
If you are already a subscriber, you can Login Here.
If you are not a subscriber, you can subscribe now, by selecting one of the below options.
For more information or assistance, please contact us at subscriptions@creamermedia.co.za.
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation