https://www.miningweekly.com

PTM to start WBJV Project 1 hot commissioning after closing $80m financing

20th November 2015

By: Henry Lazenby

Creamer Media Deputy Editor: North America

  

Font size: - +

TORONTO (miningweekly.com) – Project developer Platinum Group Metals (PTM) will start with hot commissioning of the Western Bushveld Joint Venture (WBJV) Project 1 plant, near Rustenburg, South Africa, after closing and drawing down $80-million in separate financing deals on Friday.

"We are very pleased to complete this transaction with the clear support and vision of our major shareholders. We look forward to the ramp-up of our first mine with an eye on continued solid demand for platinum and palladium and improved markets in the near and medium term,” PTM cofounder and CEO Michael Jones stated.

The TSX- and NYSE-listed company had entered into agreements with its largest shareholder Liberty Metals & Mining Holdings, a subsidiary of Liberty Mutual Insurance, for a $40-million loan facility and had also drawn down an existing $40-million working capital facility with Sprott Resource Lending Partnership.

First concentrate delivery to Anglo Platinum's Waterval smelter, in Rustenburg, was planned for January, while underground development was ongoing.

At planned steady-state production, in 2018, WBJV Project 1 was expected to be one of the lower-cost conventional platinum group metal mines in South Africa, with an expected cash cost of about $625/oz.

PTM continued to work on growth at the project, funded by the Japan Oil, Gas and Metals National Corporation, with continued drilling, resource modelling, mine design, metallurgy and infrastructure planning all under way.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION