Peru rejects EIA for Sierra Metals’ Yauricocha expansion

6th December 2018

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Toronto-headquartered Sierra Metals is facing a delay at its Yauricocha tailings expansion project, following the rejection of the environmental impact assessment (EIA) study for the deposition facility.

An approved EIA is required for a construction permit for the next three phases of the tailings dam extension, which will allow for a 20% expansion of Yauricocha’s mine output to 3 600 t/d.

The company, however, maintains that it has submitted all the required documentation and that it is optimistic that the decision will be reviewed.   

"While we are disappointed, we do not believe this decision was made with all the facts. This decision was preliminary and not based upon or including all the information submitted. Key members of the management team are going to meet with authorities to provide and demonstrate full compliance with the requirements. Management believes that once all the correct information is reviewed, we will receive a positive response from authorities," CEO Igor Gonzales said.

Sierra Metals said that the EIA delay could result in a 7% temporary shortfall in its daily ore production, compared with projects that did not include an EIA permit delay.

Gonzales noted that the expansion plans in Mexico to 3 600 t/d at Bolivar and to 1 200 t/d at Cusi were still on track and would be completed in the first quarter of 2019.

 

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION