Pan African investigating R1.7bn gold tailings project

21st September 2016

By: Martin Creamer

Creamer Media Editor

  

Font size: - +

JOHANNESBURG (miningweekly.com) – Gold mining company Pan African Resources is investigating a large gold tailings retreatment project at its Evander mines in Mpumalanga.

Underwritten proposals have been received for the full financing package for the Elikhulu project, which will require an estimated capital expenditure of R1.7-billion – without affecting the company's dividend outlook.

For the 12 months to June 30, the London- and Johannesburg-listed Pan African has reported record gold production of 204 928 oz, record 160.2%-higher profit of R547-million and record dividends of R300-million.

Following a positive, high-level economic and technical assessment of the Elikhulu tailings retreatment project, Pan African has mandated DRA Projects to complete a definitive feasibility study on the project.

Elikhulu will make use of 178.7-million tonnes of tailings that have built up over Evander’s nigh 70-year gold mining history.

“It’s a potential game-changer for Evander,” Pan African CEO Cobus Loots told Mining Weekly Online. (Also watch attached Creamer Media video).

Pan African already has an outstanding track record of delivering tailings projects, with its Barberton plant paying for itself in as few as 18 months.

Elikhulu will produce at a rate of up to 50 000 oz/y from a 1.7-million-ounce resource, as the company’s fourth tailings endeavour.

It will have a life of 14 years, with payback in three to four years, all-in sustaining costs (AISCs) of R300 000/kg and an internal rate of return of 28.6%, at an assumed gold price of R575 000/kg.

The company’s Leeuwpan dam has sufficient water for its needs and space at the existing Kinross site is seen as ideal for the deposition of residue material from the project, which has an assumed recovery rate of 45%.

The plan is for tailings to be processed at a rate of one-million tonnes a month in a carbon-in-leach plant, which is expected to take 18 to 24 months to build and commission.

“If this project does proceed, we expect first gold in November 2018,” Loots told investors and analysts.

In the 12 months to June 30, group cash costs in dollars were down 23.6% to $725/oz, AISC 20.4% lower at $870/oz, and gold resources 9% higher at 34.9-million ounces.

What makes Elikhulu quite easy for Pan African is that it is currently processing 200 000 t/m through its existing tailings plant at Evander, which provides the company with insight into exact per tonne costs and recovery percentages.

When the company pushed the button on the existing tailings retreatment plant at Evander, its market capitalisation was under R2-billion, whereas its market capitalisation now is in the R6.5-billion to R7-billion range.

In addition to Elikhulu, the company also has a number of smaller growth initiatives at Evander.

Seven shaft is a current focus area, where ramping has begun in some of the old areas and where mining of shaft pillars will commence next month, which should add to gold production.

A review of 9 Shaft, which has a resource of more than 300 000 oz, is under way to assess whether or not a return on capital can be obtained.

In the current environment, the company is putting on hold the sinking of a new vertical shaft from surface at Evander South and looking instead towards developing the highly prospective 2010 Payshoot orebody that runs parallel to the main Kinross pay channel.

A borehole from surface on to the 2010 Payshoot is in progress and results are expected in November.

A borehole sunk by former owner Harmony Gold, which historically developed towards the orebody before halting all mining operations on 7 Shaft and allowing flooding of the infrastructure to 18 level, indicated a high gold grade of 36.04 g/t over a 49 cm reef width.

“From a mining perspective, you're looking at probably about 13 g/t to 14 g/t, depending on how we mine it,” Loots commented.

If go-ahead is given ofr 2010 Payshoot, existing 7 Shaft infrastructure is in place and no completely new shaft will have to be sunk from surface.

While gold resources have been increased by nearly 10% to three-million ounces for the year, gold reserves have fallen 4% to 400 000 oz and focus on increasing gold reserves is under way.

Exploration success includes confirmation of the down dip extension of the high-grade 11 Block of the main reef complex (MRC) orebody by a further 70 m at the Fairview gold mine, in Barberton.

This will result in additional mineral reserves at Barberton and Fairview, extending the current life-of-mine (LoM) to more than 22 years.

Also encouraging is retention of the LoM of 8 Shaft at Evander at 16 years as a result of good grade and tonnage on the 25 and 26 levels.

Flashed on to a large screen was a picture of the bacterial oxidation Biox plant at the company’s Barberton mine, where oil problems have been resolved and recoveries regained.

“Barberton really is the founding and the cornerstone asset of our group at present,” said Loots.

Gold sold from Barberton’s underground and surface mines increased by 7% to 113 281 oz, with the star performer being the tailings plant, from which 18% more gold was sold at 28 591 oz at the exceptionally good all-in cost of $332/oz.

While there has been no material change in the company platinum group metals (PGM) resource of 600 00 oz, the PGM reserve has been dramatically reduced with the LoM of the Phoenix asset falling to nine years as a result of the issues the company has been experiencing with International Ferro Metal and its Lesedi underground mine.

At its Uitkomst colliery, it is accounting for more than 23-million tonnes of mineable in-situ coal made up of high-grade thermal coal with metallurgical applications.

Overall, where Pan African wants to be different is in achieving an attractive balance between sustainable profits, giving sector-leading dividend yields to shareholders and achieving growth in profitable production and gold reserves.

In comparing South Africa to other mining destinations, Loots expressed the view that the country was not always fairly judged and many of its positives overlooked.

He drew attention to South Africa’s large, world-class and long-life orebodies, excellent infrastructure and a skilled workforce and spoke of one having to go very far in West Africa to find an orebody that had a 22-year LoM such as the company had at Barberton Fairview.

He said South Africa’s environment also created opportunity, as in the Shanduka Gold transaction concluded last year, which proved materially earnings accretive to the tune of some 18%.

While Pan African has equipped and structured itself to operate successfully in South Africa, it is cognisant that geographical diversification could potentially serve to reduce the company’s perceived single country risk.

“To this end, we are actively looking to opportunities elsewhere to supplement our existing operations as well as our South African growth,” Loots added.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION