Optimised study boosts Savannah project’s output and lowers costs

20th July 2017

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – An optimisation of the feasibility study (FS) for the Savannah base metals project, in Western Australia, has lowered the expected C1 cash and operating costs of the operation, while targeting higher nickel, copper and cobalt output, owner Panoramic reported on Thursday.

Compared with a February FS, the optimised study decreased C1 cash costs from $2/lb to $1.40/lb nickel in concentrate, while operating costs have decreased from $4.50/lb to $3.10/lb of nickel.

The optimised FS also expected nickel production to increase from the previously estimated 9 700 t/y to 11 000 t/y, while copper production will increase from 5 000 t/y to 5 800 t/y and cobalt production for 670 t/y to 760 t/y.

However, the project’s mine life has also decreased from the initially estimated 10.25 years to 8.5 years, while revenue expectations have decreased from $1.5-billion to A$1.2-billion.

Savannah’s expected up-front capital requirements remained unchanged at A$20-million.

“The release of the Savannah FS optimisation demonstrates the potential for Savannah to be a financially robust project, even at today’s historically low nickel prices,” said Panoramic MD Peter Harold.

“The optimisation work focused on higher production rates, higher grade ore and lower input costs. This has resulted in an improved mine plan compared with the February FS, and has delivered significantly lower C1 cash costs and all-in sustaining costs.”

Harold said that the short lead time and minimal capital investment required to resume operations placed Panoramic in an enviable position, compared with greenfield project developers, which typically have greater funding requirements and longer preproduction development timeframes.

Panoramic in January 2016 took the decision to idle the Savannah operation on the back of declining nickel prices. The operation was placed on care and maintenance in May 2016. The FS is based on mining the remaining ore reserve at Savannah, while developing across to the Savannah North deposit.

Panoramic is now undertaking further optimisation work, which will assess a number of other initiatives that could add significant value to the project, including alternative truck technology, drilling automation and battery loaders. This work is expected to be complete during the December quarter.

In the meantime, Panoramic will continue discussions with potential offtake partners that have expressed an interest in Savannah concentrate.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION