Evander shafts back in operation after R41.5m refurbishment

12th May 2017

By: David Oliveira

Creamer Media Staff Writer

     

Font size: - +

South African gold miner Pan African Resources has completed the R41.5-million stoppage and refurbishment programme for the 7 and 8 shafts at its Evander gold mine, in Mpumalanga. Normal production has resumed.

Evander GM Tenda Tendaupenyu noted during a media briefing at the mine last month that the operation was in a much better space following the programme. “We have been going through a period of trauma in this part of the world and, out of need, we are trying to make sure that we are sufficiently resourced. This is a very old lady, so you would expect that most of the challenges we have relate to ageing infrastructure, which needs to be maintained.”

Pan African group mining engineer Bert van den Berg explained that the “mammoth” 55-day programme required a number of infrastructure items to be replaced, including 7 Shaft’s pump column support infrastructure, a damaged section of the main pump column at the 7 Shaft and the water reticulation system between 7 and 8 shafts.

Further work included the removal of redundant shaft steelwork at the 7A and 8 shafts, and cleaning and refurbishing the 7 and 7A shaft bottoms, as well as assessing all other underground infrastructure critical to maintaining and sustaining production at Evander.

Mining operations are taking place on the 23, 24 and 25 levels at 8 Shaft, while 7A Shaft is used to hoist the ore above ground.

Van den Berg pointed out that, in October last year, damage caused to the 1.8-km-deep 7A Shaft resulted in the hoisting speed at the mine dropping from 13 m/s to about 8 m/s, significantly reducing the tonnages produced at the mine.

Pan African subsequently initiated engineering studies to assess the condition of Evander’s underground mining infrastructure and reported in February that the studies had identified critical infrastructure issues that needed remedial action to ensure the safe operation of the 7 and 8 shafts.

An employee had also been killed at 7 Shaft in February when the supporting infrastructure for the pump column failed, further prompting the need for interventions.

To further reduce operating costs at the mine, Pan African completed a retrenchment programme in March, resulting in 210 voluntary and 440 compulsory retrenchments.

The mine currently has a workforce of about 1 780 people.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION