Nordgold reports y/y profit loss, lowers production guidance

30th August 2016

By: Anine Kilian

Contributing Editor Online

  

Font size: - +

JOHANNESBURG (miningweekly.com) - Diversified low-cost gold producer Nordgold’s net profit for the six months ended June 30 was down 30% year-on-year to $94.1-million, compared with the corresponding period in 2015, while half-year revenue decreased by 19% to $520.4-million for the year ended June 30.

This could be attributed to lower sales volumes and higher costs, as well as lower-than-planned production at the company’s flagship Bissa and Berezitovy mines in the period under review, which is expected to continue into the third quarter, along with the anticipated suspension of production at Aprelkovo in the second half of the year.

With this in mind, the company has lowered its 2016 full-year production guidance to between 880 000 oz and 930 000 oz from 950 000 oz to 1.01-million ounces.

CEO Nikolai Zelenski noted, however, that while Nordgold had trimmed its full-year production target after a lower-than-forecast first half, it still expected to achieve an all-in sustaining cost (AISC) guidance of between $800/oz and $850/oz.

Nordgold’s half-year earnings before interest, taxes, depreciation and amortisation decreased by 28% to $238.1-million, while gold output for the half-year was about 422 000 oz – a 17% reduction year-on-year.

The group’s average realised gold price in the first half of 2016 increased by 2% to $1 227/oz.

“Nordgold is in a strong position to take advantage of improvements in market conditions with our portfolio of high-quality mines, a strong development pipeline of significant growth opportunities and a proven operational and financial track record. I am confident our company will continue to generate consistent growth for the benefit of its shareholders," noted Zelenski.

The company reiterated its 2016 full-year capital expenditure of about $370-million, which will include investments in the construction of two mines, exploration costs, development and maintenance costs and capitalised stripping.

Meanwhile, Nordgold advised that construction on its Bouly mine, in Burkina Faso, had been completed and was currently in commissioning phase, with the launch scheduled for the third quarter of the year. 

Bouly is expected to produce an average of 120 000 oz a year for ten years at an AISC of $730/oz.

The company also launched new HiTeCC technology at Suzdal mine, in Kazakhstan, which is expected to increase production output by between 9 000 oz and 14 000 oz of gold ore a year for the next ten years.

Edited by Samantha Herbst
Creamer Media Deputy Editor

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION