Nevsun's Timok UZ PFS elevates deposit among best anywhere

3rd April 2018

By: Henry Lazenby

Creamer Media Deputy Editor: North America

     

Font size: - +

VANCOUVER (miningweekly.com) – A new prefeasibility study (PFS) on Canadian base metals producer Nevsun Resources’ Timok Upper Zone (UZ) copper/gold project, in Serbia, has confirmed the project as one of the best development-stage copper assets in the world, the company reports.

Vancouver-headquartered Nevsun reported last week that, based on an assumed copper price of $3.15/lb in 2020, when project construction is expected to start, the Timok UZ has an after-tax net present value (NPV), applying an 8% discount rate, of $1.82-billion, and an internal rate of return (IRR) of 80%.

The NPV, however, falls to $1.45-billion and an IRR of 55% when using the same price assumption in today’s market and including the $574-million pre-production capital cost. Capital expenditure (capex) excludes $114-million to be spent to reach a construction decision.

Nevsun guided that pending receipt of all required permitting, first production will take place in 2023, although the company would like to start production earlier in 2022.

On a comparative basis, the new PFS outlines a lower asset value for the project, as a result of a later start to production from 2021 envisioned in the October 2017 preliminary economic assessment (PEA) to 2023 in the latest PFS; a shorter mine life from 15 years to 10 years; higher copper refining and treatment charges and arsenic penalties; higher transport and selling costs; and higher mining, milling and general and administrative costs.

However, they are offset by somewhat lower total capex, higher life-of-mine copper and gold grades, and higher copper concentrate grades.

The mine is expected to produce 1.7-billion pounds of payable copper over a decade of operations, excluding from inferred resources, producing on average 1.89-million pounds of copper a year, at an average C1 cost of $0.92/lb of copper.

The company believes the strong front-end cash flow and quick payback period of less than one year supports a range of financing opportunities and alternatives.

Further, Nevsun advised that scoping-level work suggests the potential to decrease initial capital by up to $100-million through a staged ramp-up from 1.6-million tonnes to 3.2-million tonnes a year, while maintaining project economics.

The PFS was compiled and project managed by Hatch of Toronto, with input from SRK Vancouver, Knight Piesold in Vancouver, and Bluequest of Zug, Austria.

The PFS declared a maiden Timok UZ probable mineral reserve of 27-million tonnes at 3.3% copper and 2.1 g/t gold, based on a price of $3/lb copper and $1 300/oz gold. There remain 13.9-million tonnes of inferred resources at 1.6% copper and 0.9 g/t gold that require further drilling from underground to bring it into the higher-confidence reserve base.

Further work during the feasibility study, the results of which are expected to be released in mid-2019, will continue to refine the project and optimise costs for the construction and operation phases, Nevsun advised.

The company’s TSX-listed equity has responded positively to the Timok UZ PFS, gaining nearly 5% since Thursday and closing 3% higher on Monday at C$3.16 a share.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION