Base metals miner Lundin Mining’s Zinkgruvan zinc/lead/copper/silver mine, in Askersund, Sweden, has signed a new life cycle services (LCS) agreement with diversified engineering group Metso.

The agreement covers mill lining and related services for five grinding mills and is valid for three years. Metso reports that a ‘cost per ton’ agreement ensures that both Zinkgruvan’s and its own goals are aligned for maximum production as well as safer operations, and is the result of the “unique and long-standing partnership between the companies”.

Under the new LCS contract, five mills in total, including a new autogenous mill that was commissioned in April, will be maintained and serviced at Zinkgruvan. The new mill is expected to help increase production by 10%.

“[In terms of the contract], Metso contributes both expertise and experience. Deliveries are on time and we can rely on the quality of solutions coming from the company’s factory in Ersmark, Sweden,” says Zinkgruvan mill manager Magnus Andersson.

He notes that technology plays a central role in ensuring improved overall efficiencies at the mine. Andersson points out that Metso has delivered most of the process equipment for the mine and is involved in the entire process, from crushing, grinding and beneficiation to finished metal concentrate. He says that there are normally three fixed maintenance shutdowns a year and highlights that every stoppage costs money and therefore all unplanned downtime needs to be avoided.

“Availability is a key word for Metso. Our job is to make sure that stoppages are short and safe. With Zinkgruvan, we have a frank dialogue with fast decision-making. We are set to deliver at short notice and do our utmost to resolve any problems that might arise,” says Metso LCS manager for Zinkgruvan Urban Klitsch.

He emphasises that health, safety and environment work is the main item on the daily agenda at the mine. Klitsch comments that Metso’s service personnel are also actively working to find new measures to improve safety, noting that, for example, as an extra precaution, there is a protective structure built around the mill during a maintenance shutdown.

“Here at the plant, our preventive work brings results: our lost-time incident frequency rate is currently 1.8, which is a very good result in the industry,” Andersson concludes.

To watch Creamer Media's latest video reports, click here
 

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION