Independence confirms Nova ramp-up date
JOHANNESBURG (miningweekly.com) – The ramp-up of the Nova project, in Western Australia, has been delayed by three months, diversified miner Independence Group confirmed on Wednesday.
The company reported that the project would reach its nameplate capacity of 1.5-million tons a year in the September quarter, instead of the June quarter, but pointed out that the revised timeline remained a year ahead of the date set in the feasibility study.
Independence previously said that underground development rates had been lower than planned, but that underground contractor Barminco had taken certain actions since January to increase development rates. The average daily development rate has improved by 43% between January and March.
The miner said that Nova would produce between 5 000 t and 6 000 t of nickel and between 1 900 t and 2 300 t of copper in the 2017 financial year. The first offshore shipments of copper and nickel concentrate are scheduled to start in the June 2017 quarter.
At full production, Nova is expected to produce 26 000 t/y of contained nickel and 11 500 t/y of contained copper, at an all-in sustaining cost of A$1.83/lb. The project is expected to initially operate for ten years.
Comments
The
content
you are trying to access is only available to subscribers.
If you are already a subscriber, you can Login Here.
If you are not a subscriber, you can subscribe now, by selecting one of the below options.
For more information or assistance, please contact us at subscriptions@creamermedia.co.za.
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation