Horizontal raiseboring at Cullinan mine outperforms traditional methods

21st October 2016

By: Ilan Solomons

Creamer Media Staff Writer

  

Font size: - +

Raiseboring and drilling services group Master Drilling is nearing completion of a 220 m hole with a diameter of 4.5 m in a horizontal raisebore (HRB) trial project at Southern Africa-focused miner Petra Diamonds’ Cullinan diamond mine, in Gauteng.

During a site visit to the mine earlier this month, Petra mining manager Steven Klopper highlighted that the HRB method of developing access points to the kimberlite orebody had recorded faster development rates than traditional drill-and-blast methods in meter-per-day production targets up to date.

He explained that horizontal boring was similar to the vertical process, as conventional raisebore drilling involved the sinking of a pilot hole from the surface to an underground tunnel. Klopper pointed out that a large rotating drilling head or reamer was attached to specialised tubes of steel that were lowered down the pilot hole. The reamer was then pulled to the surface, leaving behind a shaft.

Master Drilling executive director Koos Jordaan noted that the key performance indicators for the project included the ability to drill a straight pilot hole over the length of the tunnel and to cut material, load and support the tunnel.

He said that the trial project had been running since July 2014 and, to date, a 180 m tunnel had been piloted using “a dry and accurate directional method”. Jordaan added that 30 m of reaming had been completed, with 2 m/d of tunnel development having been achieved, along with material cutting, loading and support.

“Some of the major challenges that we have had to overcome was dealing with rocky stresses, blocky ground and fines in the project area,” he said.

Further, Jordaan stated that, going forward, the aim was to increase production to 6 m/d, while also optimising the concept with regard to mobility and productivity of the HRB method. “Advances of between 9 m and 12 m seem possible.”

Other goals initiated through the use of the HRB method include tunnelling without the need for pilot holes in a straight line and mobile tunnelling at curves and different cross sections.

Master Drilling CEO Danie Pretorius pointed out that a standard vertical raise bore machine had been adapted for use in the project. However, he said that the company intended to specifically develop an HRB machine.

The remaining 40 m of the tunnel will be developed using conventional mining methods owing to challenging geology. However, the completion of the remainder of the tunnel is scheduled to be completed during the course of the next three months.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION