Gamsberg zinc prestrip close to halfway mark – Vedanta

10th October 2017

By: Martin Creamer

Creamer Media Editor

     

Font size: - +

JOHANNESBURG (miningweekly.com) – The prestripping of waste rock at the Gamsberg zinc mine project in the Northern Cape is close to the halfway mark, Vedanta Resources reported on Tuesday, when its interim CEO Kuldip Kaura described as “strong” the quarterly production performances of the London-listed, India-rooted mining company’s zinc, Copper India and aluminium businesses.

In South Africa, Vedanta subsidiary Zinc International has committed more than 80% of the $400-million capital expenditure to the first phase of the Gamsberg zinc project, which is expected to have a mine life of 13 years, and restore Vedanta’s Zinc International volumes to more than 300 000 t/y.

Vedanta reported 32-million-plus tons of waste rock had been prestripped at Gamsberg, out of a required 65-million to 70-million tons.

This is taking place at a time of a high-flying zinc price, which last week hit the $3 308.75/t mark - its highest point in ten years.

Mined metal production from Vedanta’s Zinc India in the six months to end September was a 42%-higher 452 000 t compared with the same period last year, driven by higher ore production across all mines. 

In Southern Africa, quarterly zinc production in the three months to September 30 rose to a 33%-higher 42 000 t, which was 13% higher year-on-year. Production at Skorpion Zinc in Namibia soared 66% to 23 000 t following a planned first-quarter refinery shutdown to restore the acid plant to full capacity.

Production at Black Mountain in South Africa increased to 20 000 t, a 23% better year-on-year performance, on better grades from improved drilling accuracy and higher recoveries from better operational efficiencies. 

At Skorpion, most of the equipment is in place at the pit 112 extension project, where waste mining hit record levels in the three months to September 30. 

At Copper Zambia, mined metal production was 25 000 t, a 21% quarter-on-quarter achievement. 

At the Konkola mine in Zambia, ongoing improvement in equipment availability was reported; at the Nchanga opencast mine, improved production is expected in future quarters; at the Nchanga underground mine, targeted production is expected from the third quarter onwards; and at the tailings leach plant, production increased in the current quarter on improved pump and plant availability.

Smelter use has improved on higher production and increased sourcing of third party concentrates.
 
Kaura noted that the company had begun a “growth journey” on both the exploration and development front in its oil and gas business and committed the company to ongoing operational improvement.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION