Atlas defers 4Mt/y Corunna Downs project

21st June 2017

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Iron-ore miner Atlas Iron has deferred the development of its Corunna Downs mine, with the miner instead aiming to increase production from the Mt Webber operation.

Atlas in February approved the development of the Corunna Downs project, with capital costs estimated at between A$47-million and A$53-million. The project had been slated to deliver four-million tonnes a year of lumps and fines direct shipping ore over an initial five- to six-year mine life, with first product shipments targeted for the March quarter of next year.

However, Atlas told shareholders on Wednesday that the company had deferred the Corunna Downs development, owing to the prevailing market conditions, and the approvals process taking longer than expected.

The deferral would allow Atlas to further derisk the project in anticipation of improved market conditions, MD Cliff Lawrenson said.

Instead, Atlas would look at an upgrade of the Mt Webber operation, increasing production from seven-million tonnes a year to nine-million tonnes a year, with the incremental production processed at the recommissioned Mt Dove site.

Lawrenson said that the Mt Webber upgrade was a low-cost option for the company that retained productive capacity without major capital expenditure, and that the recommissioning of the Mt Dove plant and expanding Mt Webber’s production would deliver a range of economic and production benefits.

“Utilising the Mt Dove crusher will enable Atlas to add two-million tonnes a year of production at very low capital intensity in a short period of time,” Lawrenson said.

“This enables us to achieve operating cost benefits and to maintain our 2017/18 production at levels that we would have expected prior to deferring Corunna Downs. Corunna Downs remains an important project for the company to sustain its production base and we will proceed with its development when market conditions improve”.

With mining at Abydos scheduled to end in October 2017 and the additional production at Mt Webber set to ramp up by August 2017, Atlas’s production guidance for 2018 is between nine-million and ten-million tonnes.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION