PERTH (miningweekly.com) – The definitive feasibility study (DFS) into the Arcadia lithium project, in Zimbabwe, has found that the project would require a capital investment of $165-million to develop a 2.4-million-tonne-a-year operation.

The DFS base case was double that considered in a 2017 prefeasibility study which found that an investment of $52.5-million would be required to develop a 1.2-million-tonne-a-year operation.

ASX-listed Prospect Resources on Monday reported that the DFS estimated an openpit mine life of some 12 years, with life-of-mine revenues projected at $2.93-billion and life-of-mine earnings before interest, taxes, depreciation and amortisation at $1.38-billion.

The DFS estimated a pre-tax net present value of $511-million and an internal rate of return of 44% for the Arcadia project.

“The completion of the successful DFS on a base case of a 2.4-million-tonne-a-year development of the Arcadia lithium project is a great achievement. The DFS results position the company to become a key player in the global lithium market,” said Prospect MD Sam Hosack.

He said that the DFS represented a significant milestone for the company as Prospect transitioned into development.

“We are excited by the opportunity to capitalise on the strong fundamentals of the lithium market, initially through the production of lithium concentrates. Based on the mine economics and financial strength of the project, we are moving swiftly to finance, develop and commence production at Arcadia.

Hosack said that the company has now started prefeasibility work to test the viability of a lithium chemicals plant on site, in order to upgrade the Prospect product and capture additional value from the lithium supply chain.

Prospect was hoping to be completed with the project construction by the third quarter of 2020, with commissioning to take place from November that year.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION