Weatherly Namibia mine to cost 10% less

Weatherly Namibia mine to cost 10% less

Photo by Bloomberg

15th April 2014

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

  

Font size: - +

JOHANNESBURG (miningweekly.com) – London-listed Weatherly International reported on Tuesday that the development of its flagship Tschudi opencut copper project, in Namibia, would likely cost 10% less than was stated in the 2012 bankable feasibility study (BFS).

The BFS, which was completed in December 2012, resulted in a net present value of $105-million based on an average life-of-mine (LoM) copper price of $6 067/t copper.

Weatherly said the main input costs, including mining and crushing rates, power and acid, were, on the basis of agreed contracts, about 10% below those assumed in the BFS in dollar terms.

“It is good to see that, a year on, there has actually been a reduction in the main Tschudi cost inputs and, with current copper prices still above the LoM average price used in the BFS, there should be no overall erosion in project value,” Weatherly CEO Rod Webster said.

Construction at Tschudi started in November, with the company targeting the start of production in the second quarter of 2015.

Weatherly said it was preparing to update the market on the project's financial status compared with the results of the BFS during the second quarter of 2014.

Edited by Tracy Hancock
Creamer Media Contributing Editor

Comments

Showroom

Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 
Hanna Instruments Image
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024
Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.072 0.115s - 112pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: