PERTH (miningweekly.com) – A scoping study into the Takatokwane thermal coal project, in Botswana, estimated that the mine would cost $767-million to develop, Australian junior Walkabout Resources reported on Wednesday.

The conceptual operation at Takatokwane was based on two openpit strip mines, each delivering six-million tonnes a year of coal. Some of the product would be upgraded through a modular two-stage washing plant, and the project was expected to deliver three saleable products.

The scoping study was based on the over seven-billion-tonne Joint Ore Reserves Committee-compliant resource at Takatokwane, with the mine design focused on a target mining area where 748-million tonnes had been classified as indicated resource.

“It was always important that we understood the optimum profile for mining the huge Takatokwane deposit. We now know that we will be building large-scale, opencut strip mines employing drag-lines and rope excavators that will produce coal for many years to come,” said Walkabout MD Allan Mulligan.

While the scoping study had initially opted for a 12-million-tonne-a-year production rate, Mulligan noted that this could be significantly increased in modular extensions.

Based on the 12-million-tonne-a-year output, the Takatokwane mine was currently estimated to have a net present value of $850-million and an internal rate of return of 14%.

However, Mulligan noted that the development of the Takatokwane project remained dependent on the construction of suitable rail infrastructure to move the coal product, which had been targeted for sale to South African power stations and for export through the Port of Walvis Bay, in Namibia.

The government of Botswana was currently investigating the feasibility of the Trans-Kalahari rail project, and the project was slated for completion by 2019/20.

Edited by Creamer Media Reporter

Comments

Projects

Image of lithium ore stockpile
Lithium conversion plant, Australia
Updated 1 hour 20 minutes ago By: Sheila Barradas
Aerial view of the Amapá mine
Amapá iron-ore project, Brazil
Updated 1 hour 20 minutes ago By: Sheila Barradas

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.072 0.106s - 107pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: