The La Parilla tungsten project under development in Spain is progressing as planned, with crusher, steelwork and equipment deliveries having started, Aim-listed W Resources reported on Wednesday.

In a project update, the company states that concrete and civil works have been completed for the crusher. Metso Minerals has been fabricating the crusher equipment at its plant in France and will deliver the equipment as the steel work is erected on a just-in-time basis.

Germany’s allmineral Aufbereitungstechnik, which has been awarded the contract for the jig and mill, as well as the concentrator, has started the fabrication of the primary equipment. W states that the earthworks are nearing completion for the jig and mill and work on the foundations will be completed mid to late-July with construction on schedule for the fourth quarter.

The engineering work for the installation of the concentrator has been completed. The concentrator will be completed in the first quarter of 2019.

Production from the tungsten and tin project will start in the first quarter of 2019.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.121 0.154s - 88pq - 2rq
Subscribe Now