https://www.miningweekly.com

Gamsberg project to retore Vedanta’s zinc output to 300 000 t/y from mid-2018

PROGRESSING WELL More than 25-million tonnes of the estimated 65-million to 70-million tonnes of waste rock have been excavated at the Gamsberg project

Photo by Duane Daws

PLANT CONCENTRATION About 760 m3 of concrete was poured for the raft foundation of the semi-autogenous grinding mill at the concentrator plant at Gamsberg

Photo by Duane Daws

25th August 2017

By: Mia Breytenbach

Creamer Media Deputy Editor: Features

     

Font size: - +

Diversified miner Vedanta Resources subsidiary Zinc International has committed more than 80% of the $400-million capital expenditure (capex) for the first phase of the Gamsberg zinc project, in the Northern Cape.

The first phase of the project is expected to have a mine life of 13 years, replacing the production lost by the closure of the Lisheen mine, in Ireland, and restoring Zinc International’s volumes to more than 300 000 t/y.

Mining and milling at Lisheen was concluded in December 2015 after 17 years of operation; the mine is currently in closure mode.

Prestart activities and waste stripping at Gasmberg are progressing well, with more than 25-million tonnes of the 65-million to 70-million tonnes of waste rock excavated.

Of the estimated peak of 1 500 jobs to be created during construction, more than 1 100 jobs had already been filled on site, Vedanta Zinc projects VP Satish Kumar told Mining Weekly during a site visit to the project earlier this month.

“Of the 1 153 employees on site last week, more than 58% came from the surrounding labour-sending areas,” he added.

When fully operational, the mine will permanently employ between 850 and 900 people.

The first phase will comprise an openpit mine and a concentrator plant with an ore feed rate of four-million tonnes a year. It will also comprise associated infrastructure, including a tailings dam, a waste rock dump and stockpiles, offices and workshops, a power transmission line from the Aggeneys substation to Gamsberg, a water pipeline and an access road from the N14 to Gamsberg, as well as 300 to 350 housing units.

One of the largest civil cement pours occurred at Gamsberg earlier this month, with about 760 m3 of concrete poured over a 24-hour to 30-hour period for the raft foundation of the semiautogenous grinding mill at the concentrator plant.

The concentrator is expected to produce about 250 000 t/y of zinc metal in concentrate.

Installation of the high-density polyethylene lining of the tailings storage facility started in July and was well under way, Kumar said, noting that the facility would require about 110 ha of lining.

Construction of the tailings storage facility is expected to be completed in the first quarter of 2018.

Further, construction of the water pipeline, which will run for almost 38 km from the Orange river water offtake, in Pella, in the Northern Cape, to the mine, is under way. Public water board Sedibeng will operate the pipeline.

Meanwhile, all major orders for the integrated process plant, water and power, mining and other prestart activities had been placed, the company reported last month.

Manufacturing of critical machinery, such as the mills, the crusher and transformers, is under way, with major contractors, such as Aveng Moolmans, ELB Group and Liviero Civils, mobilised to site. Site activities, including civil works, power lines and water lines, are also under way.

The project remains on schedule to achieve the first production target in mid-2018, with full production expected in 9 to 12 months.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 
Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.135 0.172s - 112pq - 2rq
Subscribe Now