Vale reveals progress in Moatize expansion and Nacala corridor development

8th March 2013

By: Keith Campbell

Creamer Media Senior Deputy Editor

  

Font size: - +

Brazilian major mining group Vale is slowing down the development of Phase 2 of its Moatize mining project, in Tete province, in Mozambique. This is to ensure that Phase 2 comes into operation in conjunction with the commissioning of the company’s new Nacala Corridor rail route, which will transport the coal from the mine to the coast for export. This was revealed in the group’s financial results report for 2012.

Moatize Phase 1 has a capacity of some 11-million tons a year (Mt/y) of coal, divided into about 70% metallurgical (or coking) coal and 30% thermal coal. Phase 2 will double these figures while retaining the same ratio of metallurgical and thermal coal. It will involve the duplication of the mine’s coal handling processing plant and related infrastructure. The civil engineering works for the stockpile area and the crusher for Phase 2 are in progress. To date, 27% of the expansion project’s physical infrastructure has been completed.

The production ramp-up at Moatize gave Vale a record coal production last year. Apart from Moatize, Vale also owns combined metallurgical and thermal operations in Australia and has minority participations (25% in each case) in two metallurgical coal companies in China. Moatize is, however, its biggest and flagship coal project.

Last year, the group’s total coal production provided 2.3% of its operational revenues, being divided into 1.8% metallurgical coal and 0.5% thermal coal. In monetary terms, coal contributed 2.11-billion Brazilian reais (R$) (about $1.07-billion or R9.62-billion), of which R$1.62-billion ($820-million or R7.38-billion) came from metallurgical coal.
In terms of volumes, the company’s metal- lurgical coal output last year came to 4 864 Mt, while the figure for thermal coal was 3 134 Mt. During 2012, Vale invested $1.25-billion into its global coal activities, of which $943-million went into projects, $207-million into maintenance and $102- million into research and development.

Regarding the Nacala corridor, the group pointed out that it had signed concessions with the Mozambique government which allowed it to accelerate the development of the railway and the associated coal export terminal at the port. The Nacala corridor project is named after the Mozambique port city that is its terminal and involves the building of new railway lines in Malawi and the rehabilitation of existing lines in Malawi and Mozambique, as well as the construc- tion of the coal export terminal. All these facilities will be majority-owned by Vale, through local subsidiaries. When completed, it will have the capacity to transport 18 Mt/y of coal.

Currently, work is already under way on the earthworks for onshore parts of the Nacala terminal, while equipment necessary for the construction of the offshore part of the terminal has arrived on site. To date, 15% of the physical infrastructure of the port has been completed. Earthworks for parts of the railway are also under way, and 12% of the physical infrastructure of the railway has been finished.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

John Deere (Pty) Ltd
John Deere (Pty) Ltd

In 1958 John Deere Construction made its first introduction to the industry with their model 64 bulldozer.

VISIT SHOWROOM 
AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.062 0.094s - 88pq - 2rq
Subscribe Now