https://www.miningweekly.com

South American miner Troy reports lower output

31st October 2014

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – Despite reporting a slight decline in production during the three months to September, ASX- and TSX-listed gold miner Troy Resources has maintained its production expectations for the financial year to the end of June 2015.

During the quarter under review, group gold production dropped to 20 624 oz, compared with the 23 057 oz produced in the previous quarter, following delays in the permitting process at the Andorinhas mine, in Brazil.

Mining from the Coruja openpit deposit only started in August this year, resulting in ore availability for the first two months of the quarter being below expectations, and the mine delivering only 5 405 oz of gold, compared with the 7 438 oz delivered in the previous quarter.

Production at the Casposo mine, in Argentina, remained on par with the June quarter, with the operation producing 15 219 oz of gold and 734 893 oz of silver. This was compared with the 15 619 oz of gold and 828 374 oz of silver delivered in the previous quarter.

“The September quarter presented several significant challenges for Troy as Casposo transitioned to full underground production, Andorinhas commenced development of the new Corja openpit and Karouni moved into top gear for the start of construction,” said Troy CEO Martin Purvis.

“Against this backdrop, it is encouraging to note that the operating teams managed to keep performance on track and within guidance, with a positive month-on-month improvement over the quarter.”

Purvis said that the company’s next objective was to consolidate this trend with further productivity improvements driving lower cash costs in order for Troy to respond to the current market levels for both gold and silver.

Edited by Creamer Media Reporter

Comments

Showroom

M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/03/2024)
15th March 2024 By: Martin Creamer
Gold, hydrogen, mining boost make headlines
Gold, hydrogen, mining boost make headlines
15th March 2024
Magazine round up | 15 March 2024
Magazine round up | 15 March 2024
15th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.115 0.148s - 106pq - 2rq
Subscribe Now