PERTH (miningweekly.com) – Mining at the Thunderbox gold mine, in Western Australia, continued to progress ahead of schedule, with owner Saracen Mineral Holdings on Wednesday confirming that the project was still slated to produce its first gold in the June quarter of next year.
First ore was mined in October, ahead of schedule, and Saracen reported that openpit mining had advanced to a depth of 40 m, with 4.46-million bank cubic metres mined to date.
The plant refurbishment was also continuing ahead of schedule and the project commissioning was on track for the March quarter of next year.
Saracen MD Raleigh Finlayson said that the progress at Thunderbox had put the company in an "outstanding" position.
“First gold from Thunderbox will see Saracen produce gold from multiple operations for the first time, doubling our production base. Importantly, this growth is both low cost, high margin, and internally funded.”
The A$65-million Thunderbox project was expected to add about 20 000 oz to Saracen’s 2016 production guidance of between 150 000 oz and 160 000 oz, and at full production would double the gold miner’s output to about 300 000 oz/y at an all-in sustaining cost of A$1 075/oz, within two years.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation