Thor lowers operating costs forecast for NT tungsten project

Thor lowers operating costs forecast for NT tungsten project

Photo by Reuters

27th November 2013

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – Junior minerals developer Thor Mining has slashed its operating costs forecasts by at least 19% at the A$73-million Molyhil tungsten project, in the Northern Territory.

Operating cost savings of up to 28% were possible if production credits for molybdenum, a potential by-product from mining at Molyhil, were taken into account, Thor reported on Wednesday.

The company initiated an internal review of the project’s cost parameters in a bid to increase Molyhil’s ore reserve, project life, financial outcomes and additional exploration upside.

The revised operating costs of ore processed were now estimated at A$72.24/t compared with A$89.51/t as defined in the project’s 2012 definitive feasibility study (DFS).

The major gains were from focusing on pre-concentrating the ore through ore sorting and a decision to pursue an owner-operator model, rather than use contract miners.

The company said it was investigating further potential savings.

After allowing for molybdenum credits, the project’s operating costs decreased to less than A$90/t compared with the A$125/t defined in the DFS.

The savings offsets come at a minor penalty in construction costs for the proposed mine, with estimated capital expenditure for Molyhil increasing by 5.5% to A$73.6-million, from A$69.7-million originally.

However, some further downwards pressure was expected from ongoing work testing new ore-sorting methods prior to processing, Thor told shareholders.

Executive chairperson Mick Billing said that the optimisation outcomes should lead to additional mining reserve and a much longer mine life for Molyhil at a time tungsten prices had remained firm during calendar 2013 with a positive longer term outlook.

“The review is timely as the 2012 DFS showed that a 7% improvement in revenue factors extends Molyhil’s ore reserves from 1.6-million tonnes to around 2.5-million tonnes and boosts the mine life a further 50% to six years,” Billing said.

“However, our own rework of the project’s financial and operating models is showing that the same gains can be achieved by reducing operating costs by A$15/t.

“To date, our cost savings initiatives have exceeded this objective and we are continuing to investigate other areas of driving costs down.”

Thor recently secured a letter of intent from US major Global Tungsten & Powders Corporation for up to 75% of the yearly production from the Molyhil mine.

The terms apply to offtake for the current planned four-year life of the mine and a right of first refusal to a two-year extension term.

The project has a total indicated and inferred resource of 4.7-million tonnes grading on average 0.28% tungsten for 13 100 contained tonnes and 0.22% molybdenum for 10 300 contained tonnes.

The DFS found that the project could produce 400 000 t/y, delivering 2 200 t/y of scheelite product and 1 250 t/y of molybdenum concentrate.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Showroom image
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

PGMs and green hydrogen make headlines
PGMs and green hydrogen make headlines
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.11 0.148s - 107pq - 3rq
1:
1: United States
Subscribe Now
2: United States
2: