PERTH (miningweekly.com) – A scoping study into the Pilot Mountain tungsten project, in Nevada, has found that the project could support a yearly throughput of 650 000 t over a 12-year operational life to generate 1 000 t/y of scheelite in concentrate, ASX- and Aim-listed Thor Mining said on Friday.

The Desert Scheelite openpit operation is forecast to produce some 7.5-million tonnes, producing scheelite concentrates and copper silver concentrates, plus zinc silver concentrates.

The scoping study estimated pre-tax profits ranging from $125-million up to $317-million from the initial openpit operations, with the higher range estimation including improved scheelite recovery, reduced mining costs at greater throughput volumes, and the potential inclusion of the Garnet deposit nearby.

The project is expected to require a capital investment of between $30-million and $35-million, with project payback estimated to take 36 months.

“I am delighted to release the results of the scoping study for the Pilot Mountain project showing potential for at least a medium-term life on one, and potentially two of the four tungsten deposits at 100% owned Pilot Mountain,” said Thor’s executive chairperson, Mick Billing.

He noted that closed circuit metallurgical testwork on Desert Scheelite ore has already start, and could potentially upgrade the results of open circuit work previously conducted, which achieved 72% recovery of scheelite and saleable quality concentrates.

“With no US domestic production, and tungsten classified by the US Department of the Interior as a critical mineral, our objective is to restart the US’ commercial mining and tungsten concentrate production after a significant break,” Billing said.

Thor will now progress the project towards a detailed prefeasibility study.

Edited by Creamer Media Reporter

Comments

Showroom

Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:3.236 3.271s - 90pq - 2rq
Subscribe Now