JOHANNESBURG (miningweekly.com) – Furnace and smelting plant manufacturer Tenova Pyromet has completed 50% of the new 20 MW platinum group metals (PGM) furnace at Northam Platinum’s Zondereinde smelter in Thabazimbi, with the handover on track for August 2017.

Project milestones achieved to date include the first steel being raised on site in mid-July 2015. This is the first of over 1 000 t of structural steelwork to be used on the project.

More than 20% of the civil structures are also complete, while the placing of the 12-m-diameter furnace shell marks another significant milestone, with the site establishment of the mechanical installation contractor.

The contract, which was awarded to Tenova in 2015, will support Northam’s planned expansion of PGM production, which requires the flexibility to process high chromite, low base metal and high-sulphur containing concentrates.

The miner will be able to operate the furnace either as a submerged arc or a brush arc operation and will, therefore, have a sufficiently broad operating range to accommodate feedstock with a widely varying mineralogy.

Tenova Pyromet’s scope on the project covers the PGM smelting furnace, feed system and offgas handling plant, as well as the furnace building and all associated civil works, infrastructure and services, electrodes, copper cooling elements and offgas handling and furnace controller.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.107 0.142s - 106pq - 2rq
Subscribe Now