Tanzania, Brazil buoy AngloGold Ashanti, South Africa lower
PRINT
 
 
Embed Code Close
content
 
7th May 2010
TEXT SIZE
Text Smaller Disabled Text Bigger
 

JOHANNESBURG (miningweekly.com) – AngloGold Ashanti posted first-quarter adjusted headline earnings of $61-million after a strong performance from its mines in Tanzania and the Americas helped offset seasonally lower production from South Africa.

"Our operations in Brazil and Argentina had another strong quarter and the turnaround progress in the US and Tanzania was also very encouraging,'' AngloGold Ashanti CEO Mark Cutifani said.

Cutifani says that the company's focus is now on improving the contribution from its South African division.

Production was 1,08-million ounces at a total cash cost of $619/oz in the three months to March 31, compared with production the previous quarter of 1,18-million ounces at $598/oz and February guidance of 1,07-million ounces at $655/oz.

The Brasil Mineraçáo operation cut costs by 12% to $369/oz, consolidating its position as the company's lowest-cost producer.

Adjusted headline earnings were $61-million, or 17c a share in the first quarter, given seasonally weak production at the South African operations after the December holiday shutdown. This compares with fourth-quarter profit of $228-million, or 62c a share, which was boosted by a once off foreign exchange gain.

AngloGold Ashanti's board approved a $195-million investment to develop its Córrego de Sítio mine in Brazil, which is expected to reach its commercial production rate of 140 000 oz/y by 2013.

A decision will be made toward the end of the year on the development of its new Tropicana project in western Australia, where exploration drilling has found new sources of gold mineralisation near the main project area, which has the potential to both increase the size of the proposed mine and its life.

Negotiations with the state gold mining company of the Democratic Republic of the Congo were successfully concluded during the quarter, prompting the initiation of a prefeasibility study for the proposed Mongbwalu mine in the country's northeastern Ituri region.

In Colombia, where the company is awaiting water permits to allow resumption of drilling on its La Colosa deposit, exploration began on several other targets and talks are under way to determine with joint venture B2Gold the best way to progress the development of the Gramalote project.

"We've got an incredible slate of new projects in the Americas, Africa and Australasia. Our focus is squarely on developing the potential that exists within our portfolio,'' Cutifani said.

AngloGold Ashanti strengthened its balance sheet post the quarter end, with the first investment-grade issue of a 30-year bond by a South African corporate. The issue of $300 million of 30-year notes and $700m of 10-year notes was more than six-times oversubscribed.

This $1-billion bond issue was completed in April, only days after the company agreed with a group of 16 banks to a $1-billion, four-year revolving credit facility, which was 1,6 times oversubscribed.

"The overwhelming appetite to provide us with long-term debt demonstrates a strong vote of confidence not only in AngloGold Ashanti, but also in South Africa.

"Wrapping up a $2 billion refinancing facility at very competitive interest rates, gives us the flexibility to focus on delivering our operating and growth commitments,'' Cutifani said.

Production in the second quarter is anticipated to be similar to that of the first quarter at a total cash cost of $650/oz.

This accounts for a previously announced interruption at the Ghanaian operations to implement a revised water management strategy and tailings facility upgrade, as well as a planned decline in output from Sunrise Dam in Australia.

Full-year guidance is maintained at 4,5-million ounces to 4,7-million ounces at a cash cost of $590/oz to $615/oz.

 

Edited by: Creamer Media Reporter

 

To subscribe to Mining Weekly's print magazine email subscriptions@creamermedia.co.za or buy now.

FULL Access to Mining Weekly and Engineering News - Subscribe Now!
Subscribe Now Login
 
 
AngloGold Ashanti CEO Mark Cutifani
 
Picture by: Duane Daws
AngloGold Ashanti CEO Mark Cutifani