Syerston proves positive for Clean TeQ

5th October 2016

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – A prefeasibility study (PFS) into the Syerston nickel and cobalt project, in New South Wales, has estimated a capital cost of $680-million to deliver average production of 18 730 t/y of contained nickel metal equivalent and 3 222 t/y of contained cobalt metal equivalent.

Owner Clean TeQ Holdings, previously known as Hot Copper, said on Wednesday that the PFS was based on a 2.5-million-tonne-a-year operation, and would have a mine life of an initial 20 years.

The PFS estimated a net present value of $891-million and a post tax internal rate of return of 25%, assuming a long-term average nickel and cobalt price of $7.50/lb and $12/lb respectively.

Clean TeQ pointed out that the nickel and cobalt resource assessed for the PFS also hosted significant quantities of scandium. However, given that the scandium market was still in development, the PFS base case assumed no scandium revenues.

Average C1 operating costs have been estimated at $2.96/lb nickel, $0.89/lb nickel after cobalt by-product credits or negative $0.76/lb nickel after cobalt and scandium by-product credits.

“The PFS has demonstrated the potential for an extremely robust project, producing metals at a scale, and in a form, that is becoming increasingly critical in energy and transport supply chains,” said Clean TeQ CEO Sam Riggall.

“Market interest in the project has been very strong, and we look forward to progressively de-risking the development plan and working with potential customers and strategic partners in these supply chains.”

The plant and infrastructure construction would take some three years, with the commissioning and ramp-up period estimated at 24 months, with production capacity expected to be achieved in the third year of operations.

While a bankable feasibility study (BFS) is being completed over the next 12 months, Clean TeQ will be undertaking a range of activities to secure financing for the development of the project.

The BFS will likely be completed in the fourth quarter of 2017, and will include a pilot campaign to produce samples of high-purity nickel and cobalt sulphate for customer testing and validation purposes.

A number of potential offtake customers have also made unsolicited inquiries about providing funding for the development of the project, Riggall said.

Edited by Creamer Media Reporter

Comments

Showroom

Flameblock
Flameblock

FlameBlock is a proudly South African company that engineers, manufactures and supplies fire intumescent and retardant products to the fire...

VISIT SHOWROOM 
Rio-Carb
Rio-Carb

Our Easy Access Chute concept was developed to reduce the risks related to liner maintenance. Currently, replacing wear liners require that...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024
Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.243 0.282s - 106pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: