Superior Lake restart feasible
PERTH (miningweekly.com) – ASX-listed Superior Lake will undertake a definitive feasibility study on its namesake project, which will be completed by mid-2019, after the restart study demonstrated that the project, in Canada, proved positive.
The study estimated that some $75-million would be required to restart the operation, with plant throughput estimated at 1 000 t/d to produce 88 000 t/y of zinc concentrate and 6 700 t/y of copper concentrate over a mine life of six-and-a-half years.
The pre-tax net present value of the Superior Lake project has been estimated at $164.8-million, while the internal rate of return has been estimated at $118.9-million.
“The restart study clearly demonstrates the Superior Lake project is one of the leading zinc development assets globally today,” said CEO David Woodall.
“The standout features of the study were the exceptionally low estimated operating costs, which is driven by the high-grade ore, as well as the low estimated initial capital costs.”
Life-of-mine operating costs have been estimated at $0.51/lb.
Woodall said that while the existing resource at Superior Lake provided an excellent platform for the company to join the ranks of zinc producers in the coming years, the company believed that the exploration potential, untested for more than 20 years, held significant value.
Further exploration will now be conducted at the base metals project, while service providers would be selected to conduct the definitive feasibility study. The company will also start the permitting process for the Superior Lake project.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation