Semafo’s Boungou mine 91% complete

19th April 2018

By: Henry Lazenby

Creamer Media Deputy Editor: North America

     

Font size: - +

VANCOUVER (miningweekly.com) – Montreal-based miner Semafo reported on Thursday that construction of the Burkina Faso-based Boungou mine, in Burkina Faso, is 91% complete, and 10% of the equipment has already been commissioned.

Commissioning exercises started in February, focusing first on the crushing circuit equipment and water services. The reclaim and grinding circuits, reagent and oxygen plants are also undergoing testing. Wet commissioning started at the end of March, with the corporation pumping water from the water storage facility to the raw water tanks for the processing plant.

The company said it is still on track to pour the first gold early in the third quarter.

Development continues to track on budget, with $194-million of the $231-million capital expenditure incurred.

Semafo advised that it has started recruiting mine operator employees and training started in April, and is expected to be completed by May.

Pre-stripping is 77% complete, with 14-million of the projected 18-million tonnes extracted. The first ore will be hauled and placed on the run-of-mine pad at month-end.

Edited by Creamer Media Reporter

Comments

Latest News

The integration of Alamos' Island Gold mine (pictured) and Argonaut's Magino mine will create synergies of $515-million.
Alamos buys rival Argonaut
27th March 2024 By: Mariaan Webb

Showroom

Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 
John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.159 0.194s - 106pq - 2rq
Subscribe Now