Renard diamond project, Canada

12th May 2017

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the project
Renard diamond project.

Location
Quebec, Canada.

Client
Stornoway Diamonds.

Project Description
The project is located about 250 km north of the Cree community of Mistissini and 350 km north of Chibougamau, in the James Bay region of north-central Quebec.

The project hosts probable mineral reserves, as defined under National Instrument 43-101, of 22.3-million carats. The reserves are derived from 30.2-million carats of indicated mineral resources.

The November 2011 feasibility study included ramp and shaft access to the Renard underground mine. According to the optimisation study released in January 2013, shaft sinking will be deferred until later in the mine life and access to the underground mine will be through a ramp only.

The shaft will be developed to a depth of 610 m, sufficient to extract all mineral reserves and the inferred mineral resources. It will also be enlarged to accommodate the planned production rate of 6 000 t/d of ore.

Ore will be hauled to surface by 60 t trucks, with ramp ventilation capacity and surface maintenance facilities expanded to accommodate the increased fleet. Plant capacity remains at 6 000 t/d, expandable to 7 000 t/d. Power requirements, provided through on-site diesel power generation, are expected to total 12.2 MW during operations.

The optimisation study further states that diamond production in years 1 and 2 will be derived predominantly from the Renard 2/3 openpit. Diamond production from the underground mine will start during Year 2. As indicated in the feasibility study, underground ore will be mined, with blast-hole shrinkage on the 250 m, 430 m and 610 m development levels, and waste backfill from surface. The optimisation study contains a refined draw-point design and a mining sequence, incorporating a panel-retreat method to better ensure geomechanical stability and mitigate the unexpected onset of natural caving.

According to a revised mine plan and technical report, dated March 2016, Renard is expected to produce an average of 1.8-million carats a year over the first ten years of mining at an average valuation of $155/ct. The mine will produce 1.6-million carats a year for the remainder of its 14-year mine life.

An expansion to 7 000 t/d, or 2.52 million tonnes a year, is scheduled for 2018 based on achieving an 83.5% utilisation and an additional 2% throughput increase.

The additional ore feed will be derived from the Renard 65 kimberlite, where openpit mining operations for sourcing construction aggregate have been under way since 2014.

Renard 65 will provide supplementary ore feed from 2018 to 2029 from an openpit developed to a depth of 155 m, with a stripping ratio of 2.11.

No underground mining is currently contemplated at Renard 65.

Processing of low-grade stockpiles derived from the mining of CRB and CRB2a in the Renard 2/ 3 openpit will be available to extend the mine life to 2030, which would be expected to be deferred upon the addition of further mineral resources to the mine plan. 

Once complete, the project will be the first diamond mine in Quebec, and one of only six in Canada.

Jobs to be Created
The project will employ about 600 people.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at 7% discount rate, of $974-million, as at January 1, 2016.

Value
The initial capital cost estimate of the project is C$775-million and the life-of-mine capital cost estimate is C$1.05-billion.

Duration
Construction began on July 10, 2014, following the completion of a C$946-million project financing transaction.

The project achieved commercial production on January 1, 2017.

Latest Developments
Stornoway Diamonds has issued its maiden first-quarter operating and financial results report, showing that mining rates, development progress in the underground mine and carat production continue to exceed plan.

The company, which declared commercial production at its flagship Renard diamond mine on January 1, recovered 385 151 ct during the quarter from the processing of 419 233 t of ore, for an attributable grade of 92 carats per hundred tonnes (cpht), compared with a plan of achieving 369 307 cts at 91 cpht.

During the quarter, mining in the Renard 2/3 and Renard 65 openpits comprised 1.25-million tonnes, or 112% of plan, with 625 576 t of ore extracted. Underground mine development comprised 1 459 m, or 113%, of the plan.

Key Contracts and Suppliers
SNC-Lavalin (EPCM).

On Budget and on Time?
The project is on schedule.

Contact Details for Project Information
Stornoway Diamonds director of investor relations Orin Baranowsky, tel +1 416 304 1026 or email info@stornowaydiamonds.com.
SNC-Lavalin, tel +1 514 393 1000 or fax +1 514 866 0795.

Edited by Creamer Media Reporter

Comments

Showroom

Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 
Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.108 0.141s - 90pq - 2rq
Subscribe Now