Pilgangoora delivers first coarse product
PERTH (miningweekly.com) – ASX-listed Pilbara Minerals has produced its first coarse concentrate from the Pilgangoora lithium project, in Western Australia.
The first coarse production followed on from the first fines concentrate last month, and resulted from the coarse circuit being brought on line.
A total of some 1 000 t of coarse and fines concentrate has been produced to date.
The company said on Tuesday that with each primary sub-circuit of the Pilgangoora concentrator having now been operated, commissioning of the plant can now move forward to completion, then to product specification optimisation and production ramp-up.
As part of completing the commissioning process and product specification optimisation, fines concentrate will now undergo final processing through the dressing circuit, which is one of the last sub-systems to be commissioned within the concentrator.
Fines concentrate will be assayed following final commissioning of the spodumene concentrate dressing circuit. Assays are awaited for the coarse concentrate production.
“The extensive planning and due-diligence undertaken by our engineering, construction and production teams is now well and truly paying dividends as we progressively bring the plant on line and ramp up its capacity,” said Pilbara MD and CEO Ken Brinsden.
“We look forward to the successful delivery of our first high quality concentrate products to our customers next month,” he added.
The Stage 1 project at Pilgangoora will be a two-million-tonne-a-year operation, producing an average of 314 000 t/y of 6% spodumene concentrate and 321 000 lb/y of tantalite, over 36 years. The Stage 2 expansion will increase production to five-million tonnes a year.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation