PERTH (miningweekly.com) – A scoping study has estimated that the Pilbara gold project, in Western Australia, will require A$78-million to build a mine producing 290 000 oz over five years.

ASX-listed De Grey mining told shareholders on Friday that the scoping study was based on an openpit mining operation and a purpose-built one-million-tonne-a-year oxide carbon-in-leach plant.

A sulphide and flotation and regrind circuit would be added in the third year of the operation, which would cost an additional A$18-million and would be funded from cash flow.

Yearly gold production would range from between 65 000 oz in the first year and 51 000 oz in year four.

“The scoping study results, using reasonable assumptions, are highly encouraging. The project currently shows a five-year openpit mine life, but there is clear potential for significantly increased cash flow through increases in mine life, which we expect to achieve through the company’s current resource programme,” said De Grey chairperson Simon Lill.

He noted that further substantial upside was seen in improved mine scheduling, increased economies of scale, inclusion of low capital cost heap leaching of low-grade mined material, and potentially improved recoveries within the sulphide material.

The scoping study was based on a resource of 4.8-million tonnes, at 2.1 g/t gold for 325 000 oz.

A prefeasibility study into the Pilbara gold project has now been launched, to be followed by a definitive feasibility study.

Edited by Creamer Media Reporter

Comments

Showroom

Flameblock
Flameblock

FlameBlock is a proudly South African company that engineers, manufactures and supplies fire intumescent and retardant products to the fire...

VISIT SHOWROOM 
Rio-Carb
Rio-Carb

Our Easy Access Chute concept was developed to reduce the risks related to liner maintenance. Currently, replacing wear liners require that...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024
Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.224 0.265s - 88pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: