PERTH (miningweekly.com) – Metals miner Independence Group has produced its first concentrate at the Nova nickel/copper project, in Western Australia’s Fraser Range.

“The production of first nickel and copper concentrate is a key milestone for the Nova project. Based on the definitive feasibility study, the first concentrate was not scheduled to be produced until December 4, but this milestone has now been achieved, some six weeks ahead of plan,” Independence CEO and MD Peter Bradford reported on Wednesday.

Commissioning of the Nova nickel processing plant also started about four weeks ahead of schedule, and despite the fast-tracked development, the project has remained on budget at A$443-million.

The next key milestone for the processing plant will be the performance testing, which will start in November with practical completion likely to be achieved in December.

“Our near-term focus is on demonstrating steady-state operations at design throughput rates and production of nickel and copper concentrates at the design grade, specifications and recovery. This will be followed by delivery of nameplate capacity in accordance with plan by mid-2017.”

The first shipment of nickel concentrate to BHP Billiton Nickel West is expected in December, while the first offshore shipment of copper and nickel concentrate will be made in early 2017.

The underground mine is also expected to ramp up to full production by mid-2017.

At full production, Nova is expected to produce 26 000 t/y of contained nickel and 11 500 t/y of contained copper, at an all-in sustaining cost of A$1.83/lb. The project is expected to initially operate for ten years.

Meanwhile, Independence on Wednesday reported an 11% decline in quarterly revenues for the three months to September, as a result of the timing of shipments, which resulted in lower zinc revenue from the Jaguar mine, in Western Australia.

Total revenue for the quarter reached A$92.8-million, down from the A$105.9-million reported in the June quarter.

The Jaguar mine delivered A$30.8-million in revenue during the quarter, while the Tropicana gold mine delivered a further A$43.2-million and the Long nickel mine some A$19.6-million.

The Jaguar mine produced 10 309 t of zinc and 1 887 t of copper during the quarter under review, compared with the 8 937 t of zinc and 3 235 t of copper produced in the previous quarter.

Gold production from the Tropicana joint venture, in Western Australia, increased from 95 133 oz in the June quarter to 100 038 oz during the three months to September, while the Long operation, also in Western Australia, produced 2 166 t of nickel, compared with the 2 018 t delivered in the previous quarter.

“This was an excellent quarter for Independence with all mines delivering at or better than guidance,” Bradford said.

He noted that in addition to first concentrate production at Nova, Independence’s investment to expand the processing capacity at Tropicana, and to extend the project’s mine life, was also well advanced.

Commissioning of two additional carbon-in-leach tanks, which represents the final stages of the processing plant optimisation work, was completed in October.

“We are approaching a very exciting time for Independence with a number of major value catalysts ahead,” Bradford said.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

Showroom

GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.068 0.1s - 106pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: