https://www.miningweekly.com

NICO gold/cobalt/bismuth/copper mine project, Canada

27th January 2017

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
NICO gold/cobalt/bismuth/copper mine project.

Location
Northwest Territories, Canada.

Client
Fortune Minerals.

Project Description
The proposed NICO mine is located 50 km north of the Tlicho community of Whati and 160 km north-west of Yellowknife, in Canada’s Northwest Territories.

The NICO deposit contains openpit and underground proven and probable mineral reserves totalling 33-million tonnes, containing 1 085 000 oz of gold, 82-million pounds of cobalt, 102-million pounds of bismuth and 27-million pounds of copper. At the planned mill throughput rate of 4 650 t/d of ore, the mineral reserves will sustain operations for 19.8 years.

Openpit methods will be used, with underground ores contributing 22% of the mill feed during the second year of operations. The openpit part of the mine will be a conventional truck-and-shovel/loader operation, accomplished in four phases at an average waste-to-ore strip ratio of 3.0:1.

The underground portion of the mine will be mined by a contractor usingretreat blasthole open stoping, providing access to gold-rich, higher-grade ores.

The ore will be processed in two stages at the NICO site and Saskatchewan metals processing plant (SMPP). At the NICO site, an average of 4 650 dry tonnes a day of ore will be processed in a crushing, grinding and flotation concentrator to produce about 180 t/d of wet bulk concentrate.

The bulk concentrate will be bagged and transported by truck to Hay River, Northern Territories, for transfer to rail and delivery to Fortune’s proposed SMPP on the CN main line, near Saskatoon, where the concentrate will undergo additional grinding and flotation to produce separate gold-bearing cobalt and bismuth concentrates.

The cobalt concentrate will be processed by pressure acid leach in an autoclave to dissolve the metals. The pregnant solution that is produced will be treated with lime sequential neutralisation to remove impurities and then with sodium carbonate to precipitate cobalt carbonate. This carbonate is releached in sulphuric acid to a produce cobalt sulphate solution, which is purified further through ion exchange and the cobalt precipitated using electrowinning to cobalt cathode that is 99.8% purity.

Alternatively, the cobalt that is present as a sulphate in solution can be processed further through solvent extraction to remove metal impurities, followed by crystallisation, to generate 20.9% cobalt sulphate heptahydrate crystals.

Copper that is removed from the cobalt solution during neutralisation is releached in acid and precipitated onto iron fines as a copper metal precipitate or ‘cement’.

The bismuth concentrate is treated using atmospheric acid leach, followed by electrowinning to produce 99.5% bismuth cathode, which is melted and poured to produce 99.99% bismuth ingots.
Jobs to be Created
Not stated.

Net Presents Value/Internal Rate of Return
Not stated.

Value
C$589-million-plus working capital.

Duration
According to the National Instrument 43-101 technical report completed on the project in July 2012, the mine production schedule assumes that openpit waste stripping will begin in July 2015, openpit ore production in September 2015, underground dewatering and rehabilitation of existing workings in May 2016, underground ore and waste development in June 2016 and underground stoping in July 2016.

Underground ore production will end in January 2017, while openpit ore production will end in 2035.

Latest Developments
Fortune Minerals has appointed PricewaterhouseCoopers Corporate Finance (PwCCF) to help secure the working capital of more than C$589-million required to build its flagship Nico cobalt/gold/bismuth/copper project.

Fortune believes that the recent announcement of federal government funding for a public road to the community of Whati, which is critical to establish mine operations, and the positive momentum in cobalt and gold markets, will enable the company to proceed with financing construction of the project.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Fortune Minerals investor relations manager Troy Nazarewicz, tel +1 519 858 8188, fax +1 519 858 8155 or email info@fortuneminerals.com.
 

Edited by Creamer Media Reporter

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Universal Storage Systems (SA)
Universal Storage Systems (SA)

South African leader in Steel -Racking, -Shelving, and -Mezzanine flooring. Universal has innovated an approach which encompasses conceptualising,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.179 0.21s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: