Newstrike Capital reports robust PEA for Ana Paula, Mexico

Newstrike CEO Richard Whittall

Newstrike CEO Richard Whittall

15th September 2014

By: Creamer Media Reporter

  

Font size: - +

JOHANNESBURG (miningweekly.com) – Precious metals company Newstrike Capital on Monday reported that the results of an independent technical report for a National Instrument 43-101 preliminary economic assessment (PEA) supported its view that Ana Paula was one of the best development-stage gold projects in Mexico.

The company explained that the study, conducted in accordance with CIM guidelines, indicated that Ana Paula, in the Guerrero Gold Belt, was a robust, high-margin, rapid-payback, 8.2-year openpit mining project that benefitted from high gold grades with a low strip ratio. Further, the Ana Paula project had “excellent” access to infrastructure and was located in an established mining jurisdiction.

"It is a straightforward openpit mine, using conventional milling and flotation concentration with robust economics. The combination of high gold grades, low capital requirements and low operating costs makes this a compelling development project," commented Newstrike president and CEO Richard Whittall.

"With a positive PEA in hand, our next step is to evaluate the significant underground potential at Ana Paula and to support high-priority exploration targets in this prolific gold belt."

Newstrike’s management viewed the economics concluded by the PEA as a strong incentive for continued geotechnical, metallurgical and engineering studies. The company believed there were excellent opportunities to refine various project elements and improve the economics through gold recovery optimisation.

Newstrike expected an average production of 116 000 oz/y gold and 239 000 oz/y silver over a 8.2-year mine life.

Life-of-mine (LoM) average head grades were forecast to be 2.24 g/t gold and 6.89 g/t silver, with LoM gold and silver recoveries of 75% and 50%, respectively. The LoM strip ratio was calculated at 2.6:1 of waste to mineralised material.

According to the PEA, the openpit mine, which would produce 6 000 t/d using a gravity/flotation/carbon-in-leach process plant and have cash costs of $527/oz of gold, $486/oz of gold net of by-product credits, with all-in sustaining costs of $567/oz of gold, $526/oz of gold net of by-product credits.

Using a base case of $1 300/oz of gold and $20/oz of silver, the Ana Paula project would have a pretax net present value (NPV) at a 5% discount rate of $405.3-million and an internal rate of return (IRR) of 47.5% with a two-year payback. After-tax NPV at a 5% discount rate was $232.1-million, while the IRR would be 32.8% with a 2.4-year payback.

Initial preproduction capital costs  were $163.9-million over the total LoM and increased to $219.7-million when including sustaining/closure costs of $55.8-million.

The Ana Paula project is roughly half way between the cities of Mexico City and Acapulco. Mexico is a favourable jurisdiction for mining investment with clearly established mining law and regulatory due process as demonstrated by the existence of operating gold mines such as Goldcorp's Los Filos, in close proximity to Ana Paula. Further, Torex Gold's El Limon/Guajes mine is currently under construction in close proximity to the project.

Conventional openpit mining methods would be employed. Mining would be contracted, so no capital was included for mining equipment, instead contractor mining rates were used as the basis for mining costs. Openpit mining costs were calculated from first principles based on equipment required and included pit and dump operations, road maintenance, mine supervision and technical services cost.

The resource is based on 223 diamond core drill holes, aggregating 108 832 m and containing 77 183 assay intervals, of which effectively all were assayed for gold and silver. The mineral resource estimate had an effective date of August 8.

The PEA study was prepared by JDS Energy & Mining under the direction of Newstrike project development VP Thomas Bagan.

Newstrike highlighted that the PEA mine plan and economic model included the use of inferred mineral resources that were considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorised as mineral reserves and there was no certainty that the PEA would be realised.

Edited by Tracy Hancock
Creamer Media Contributing Editor

Comments

Showroom

Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 
Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

PGMs and green hydrogen make headlines
PGMs and green hydrogen make headlines
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.133 0.172s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: