New shaft at GoldStone’s Akrokeri will allow access to historic high-grade gold mine

10th July 2018

By: Simone Liedtke

Creamer Media Social Media Editor & Senior Writer

     

Font size: - +

A new shaft is being sunk at Aim-listed GoldStone Resources’ Akrokeri-Homase gold project (AKHM), in Ghana, to a target depth of 30 m.

The Norton shaft will allow access to the historic high-grade Akrokeri underground gold mine, one of two previously producing operations at AKHM, to enable the company to complete a geological assessment of the mine.

As at July 6, the Norton shaft had been sunk to 20 m below surface, with 19 m fully timbered and partitioned.

Owing to the ongoing deepening of the Norton shaft, an electric driven winch is being installed to assist with the extraction of the materials.

Further, work at the historic North shaft at Akrokeri is currently under way to ascertain if this shaft can be re-opened for use by Goldstone. 

Depending on the state of the shaft, it may be used as a second point of egress, for ventilation purposes and also to gain access to the old underground mine workings.

“With Ghana’s Parliament recently ratifying the regulatory and fiscal agreements for the redevelopment of our neighbour, the Obuasi gold mine, and the issuing of their environmental permit, the attitude in Ghana towards mining is increasingly positive, reinforcing the backdrop to our strategy of rapidly advancing the project and achieving production within two years,” GoldStone CEO Emma Priestley said on Tuesday.

In terms of the environmental base line study, GoldStone has started the terrestrial baseline work for the environmental- and social-impact assessment (Esia), which will support further development at AKHM, which is ahead of intended production within two years.

The collection of the required data is to ensure the most expedient and thorough approach to completing AKHM’s environmental impact statement (EIS) in respect of permitting.

The collection stations have been mobilised and a full-time Esia assistant has been employed, the company noted. 

The EIS is one of the requirements for the application of the mining licences.

Once the baseline data is collected, GoldStone will engage in additional dialogue with the local communities to optimise AKHM’s benefits and minimise the impacts associated with AKHM’s construction and subsequent operations.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.151 0.185s - 106pq - 2rq
Subscribe Now