https://www.miningweekly.com

Minera IRL optimises flagship Ollachea project in Peru

Minera IRL optimises flagship Ollachea project in Peru

Photo by Minera IRL

4th June 2014

By: Henry Lazenby

Creamer Media Deputy Editor: North America

  

Font size: - +

TORONTO (miningweekly.com) – Triple-listed Minera IRL on Wednesday revealed improved plans for its flagship Ollachea gold project, in Peru, saying that despite the project’s expected life remaining similar to the 2012 definitive feasibility study (DFS), several areas benefitted from the optimisation process.

The Lima, Peru-based firm said that the updated mine plan, prepared by international consultancy Mining Plus, had resulted in an optimised ramp-up with the average yearly gold output increasing to 100 000 oz over the first two years, up from 70 500 oz in the Ollachea DFS.

The average yearly output would top 100 000 oz over the nine years of mine life, almost identical to the Ollachea DFS.

Total gold output rose to 930 000 oz, up marginally from 921 000 oz.

The initial capital cost of the project was pegged at $164.7-million, down from $177.5-million, and the mine would produce yellow metal at an average total cash cost of $587/oz, slightly up from $583/oz.

Ollachea has an after-tax net present value, at a 7% discount rate and gold price of $1 300/oz, of $181-million, up 17% from $155-million. The internal rate of return is 28.2%, up from 22.1%.

With the new scenario in place, the payback period decreased to 3.1 years, from 3.7 years.

The company, which has stock listed on London's Aim, the Lima Stock Exchange and the TSX, now expected production to start in the second quarter of 2016, as opposed to the first quarter.

“The resulting optimised underground mine design and production schedule … has allowed us to bring forward considerable gold production. This, along with $9.5-million of deferred capital, has enhanced the project's financial projections,” executive chairperson Courtney Chamberlain said.

He added that the company was confident that it would “soon” receive the construction permit, while its effort on the debt restructuring and project financing continued.

“Based on the optimisation just completed, and assuming that financing is in place and project development can commence in the third quarter of 2014, the latest schedule indicates that construction should be completed within 21 months, or the first quarter of 2016 [from late 2015], with a ramp-up to full production in the second quarter of 2016 [from the first quarter of 2016],” Chamberlain noted.

Trading at C$0.155 apiece on Wednesday, the company’s TSX-listed stock is down 20% so far this year.

Edited by Creamer Media Reporter

Comments

Showroom

Showroom image
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (12/04/2024)
12th April 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.102 0.137s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: