Lydian hits Amulsar milestones as construction proceeds apace

20th June 2017

By: Henry Lazenby

Creamer Media Deputy Editor: North America

     

Font size: - +

VANCOUVER (miningweekly.com) – Construction of Lydian International’s 100%-owned Amulsar project, in Armenia, is advancing fast with 58% of the $369.9-million project capital committed as of May 31.

Priority will now shift to advancing site earthworks.

The Toronto-headquartered company reported on Monday that construction continues to accelerate and employment will top 1 300 workers later this year.

Lydian said it had completed work on primary site access roads, the adsorption desorption refining (ADR) plant platform, the construction warehouse platform and the heap leach facility (HLF) temporary sediment dam. Earthworks and construction activities have started on the platform for the crushing and screening plant and in other areas at higher elevations.

Construction power and water are in place, access roads are complete, the construction warehouse has been erected and detailed design and fabrication of the electrical distribution equipment is in process, the company reported.

As the hot summer months approach, personnel will be accommodated in a local 250-bed hotel used for initial worker accommodations and which has been renovated, while the 680-bed permanent residence camp is expected to be completed and occupied later this summer.

Lydian further pointed out that the design of the mine haul road was now complete and the construction contract awarded.

Caterpillar is ahead of schedule in producing the primary mine mobile equipment, and initial deliveries are expected to start in late July. The mining fleet for Amulsar will include, among other things, 19 Caterpillar 789D 180 t capacity haul trucks, one Caterpillar 994 front-end-loader, and two Caterpillar 6040 hydraulic shovels. A training simulator has been bought to train equipment operators.

Further, the design and fabrication contracts for the crushing and screening plant and the overland conveyor system have been awarded. Fabrication of the equipment components is in process, and the first shipment of structural steel for the crushing plant was delivered to site on schedule. Earthworks preparing the crushing and screening plant building platform are in progress.

Lydian has also completed design of the HLF and the contract for the earthworks has now been awarded. The contractor has mobilised to site and has started topsoil stripping. The contract for supplying and installing the geomembrane liner for the HLF and associated process ponds has also been awarded.

Meanwhile, Lydian reported that it has awarded the contract for the design and supply of the ADR plant, and equipment construction is under way.

The company also announced that the Amulsar project is advancing its application to secure pre-operational certification under the International Cyanide Management Code with positive assessments by an International Cyanide Management Institute- (ICMI-) listed third-party auditor and a commendation by the ICMI on its commitment to the Cyanide Code and its pursuit of pre-operational certification.

Lydian’s TSX-listed stock added a penny on Monday, closing up 4.84% at C$0.32 a share.

Edited by Creamer Media Reporter

Comments

Showroom

John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.126 0.162s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: