TORONTO (miningweekly.com) – TSX-listed exploration and development company Klondex Mines on Monday said it had achieved two significant milestones at its Fire Creek project by delivering the first shipment of ore to Newmont Mining for processing and by converting the complex to use electrical grid power instead of generator power.
The first shipment of 1 000 t of Fire Creek material to Newmont began on August 5. Klondex expected to receive payment for this shipment in the third quarter.
Further, the power line was now fully connected and energised by way of the Klondex-owned substation, which was built in 2012. The substation was connected to the Nevada Energy electrical grid earlier this year.
As a result of this achievement, Klondex said it now expected increased efficiencies in its development work, as well as a significant reduction in the unit cost for electricity.
"We're extremely pleased with the timely progress the team is making during this pivotal year for Klondex. Processing the Fire Creek material through Newmont's milling facility allows us the opportunity to monetise the mineralised material from the underground development programme,” Fire Creek GM Mike Doolin said in a statement.
He added that energising Fire Creek with grid power allowed greater flexibility and support for its increasing power needs as the operation continued to develop.
“Assuming our consumption increases on average by 30% and the unit cost decreases to $0.12/kWh, we expect to realise a saving of about 25% of the current power costs,” he noted.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation