Kin exercises option to buy idled Gold Field plant for Leonora

30th June 2017

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

JOHANNESBURG (miningweekly.com) – Gold developer Kin Mining has exercised its option to buy the idled Lawlers gold processing plant from Gold Fields’ Agnew mine for A$2.5-million.

The company intends to use the 800 000 t/y plant, which had been on care and maintenance for about two years, at its Leonora gold project, which is located about 160 km by road from the Agnew mine.

Kin announced in April that it had executed an option agreement to purchase the processing plant and was granted an exclusive option agreement.

Kin MD Don Harper said on Friday that the purchase of the plant was a key step towards production at Leonora.

“We continue to generate exceptional drilling results, which highlight immense potential to grow inventory at Leonora and remain on track to complete the Leonora definitive feasibility study in the September quarter of this year,” he commented in a statement.

The company completed a prefeasibility study for Leonora in December, which demonstrated its potential to be a low-risk, high-margin gold project. The mine will have an initial life of 6.5 years, producing 43 000 oz in year one and ramping up to 52 000 oz in year three. The preproduction capital cost was estimated at A$35-million.

Edited by Creamer Media Reporter

Comments

Showroom

Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.099 0.13s - 88pq - 2rq
Subscribe Now