JV nears completion of Agata nickel processing plant DFS
JOHANNESBURG (miningweekly.com) – TSX-V- and Frankfurt-listed Mindoro Resources says its subsidiary, Agata Processing Inc (API), expects to complete a definitive feasibility study (DFS) for a nickel processing plant at the Agata project, in northern Mindanao, Philippines, by the end of this year.
TVI Resource Development (TVIRD) was the operator of the nickel processing plant project and had the right to earn a 60% interest in API from Mindoro.
The proposed plant would make use of a two-stage process, involving atmospheric tank leaching and low-pressure acid leaching, to process nickel. The two-stage process was specifically engineered by TVIRD in an effort to reduce the capital expenditure (capex) requirement for the project.
The joint venture (JV) partners expected to invest between $150-million and $200-million in capex to establish the plant, which would have the capacity to produce 7 000 t/y of nickel-equivalent product.
Mindoro pointed out that high-pressure acid leaching nickel processing plants required capex of more than $1-billion to establish.
“We are extremely pleased with the progress being made by the API JV in nearing completion of the DFS.
“Building on the current high iron/low nickel direct shipping ore (DSO) operation, the proposed nickel processing plant would receive feed from the same mining site and produce an intermediate nickel product at low costs. We look forward to completion of the DFS by the end of the year and the significant value we believe it will add to Mindoro's Agata project,” said Mindoro CEO Penny Gould.
The existing DSO operation at Agata was focused on the upper zone of the Agata laterite orebody.
The proposed nickel processing facility would process ore from the lower limone and saprolite zones to produce a mixed hydroxide product with about 40% nickel content, which would be sold to the stainless steel market.
Once the DFS had been completed, TVIRD would move into the detailed plant design and construction phases.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation