JOHANNESBURG (miningweekly.com) – Aim-listed Hummingbird Resources has awarded the structural, mechanical, plate work and piping (SMPP) contract for its Yanfolila gold project, in Mali, where mine construction is currently under way, to construction company Imagri-SARL.

The company on Thursday noted that plant construction was on track, with completion planned for the fourth quarter, ahead of its first gold pour expected by the end of the year.

Hummingbird CEO Dan Betts said the company was “making great progress” on the ground. “We are delighted to have appointed Imagri-SARL for the important SMPP contract, having already seen their excellent results from the civil works on site,” he said.

Steelwork has also started to arrive at Yanfolila, with the carbon-in-leach tanks to be assembled soon. “In the mean time, we look forward to welcoming a number of mining analysts and investors on site at Yanfolila next week at this exciting time for Hummingbird,” said Betts.

Much of the mechanical equipment has also now been ordered and many items are now being shipped to site. The tower crane, which will be used to help build the plant and later maintain the plant when in operation, is now on site.

To facilitate mining, the drilling of the pit dewatering bores has started and the pit dewatering is scheduled to start in the second quarter.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.13 0.164s - 88pq - 2rq
Subscribe Now