Grange output falls, costs rise on maintenance shutdown

29th July 2016

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

  

Font size: - +

JOHANNESBURG (miningweekly.com) – Production at the Savage River mine, which ASX-listed Grange Resources owns and operates in Tasmania, fell in the June quarter, owing to a planned maintenance shutdown, which added to costs in the three-month period.

Grange produced 520 525 t in the June quarter, compared with 639 517 t in the March quarter, while unit costs increased to A$89.11/t, from A$63.27/t in the previous quarter. The company explained on Friday that the increase in unit costs was consistent with the lower output and the costs associated with the planned maintenance programme.

The miner shipped 795 745 t of iron-ore in the quarter, which is an increase on the previous quarter’s shipments of 670 433 t. The average price received during the quarter was $67.69/t, up 11.7% on the $59.02/t achieved in the March quarter.

Grange stated that the upward movement in prices reflected an increased demand for the company’s high-quality, low-impurity products, which had resulted in the pellet premium strengthening, together with the rebound in benchmark 62% iron content prices.

“The price of iron-ore slightly recovered in the quarter, although it remains volatile. The company continues to focus on cost reduction, while maintaining a safe and sustainable operation,” commented CEO Honglin Zhao.

Edited by Creamer Media Reporter

Comments

Showroom

Actom image
Actom

Your one-stop global energy-solution partner

VISIT SHOWROOM 
Showroom image
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.102 0.143s - 88pq - 2rq
Subscribe Now