Name and Location
Ghaghoo underground diamond mine, Botswana.

Client
Gem Diamonds, through its wholly owned company, Gem Diamonds Botswana.

On July 25, 2011, Gem Diamonds announced the name change for its wholly owned Gope Exploration Company to Gem Diamonds Botswana. Gope Exploration Company holds the mining licence for the Gope deposit, which has been renamed Ghaghoo diamond mine.

Project Description
Originally scoped as a six-million-tonne opencast mine, following the global financial crisis in 2008, Gem Diamonds’ board undertook to review all capital projects and decided to develop a small underground mine instead of a large-capital openpit operation.

Based on the revised plan, the Botswana government granted the company a 25-year mining licence at the end of 2010.

The Ghaghoo mine is being built as an underground mine in a phased manner to take advantage of the Ghaghoo diamond deposit, which comprises a 2.1-million-carat mineable reserve, with an average grade of 27.81 carats per hundred tonnes at an average diamond price of $267/ct.

The mine is situated near the south-eastern border of the Central Kalahari Game Reserve, a remote area characterised by arid and difficult road conditions. To minimise the capital spend on Phase 1 of the mine, an access decline was selected as the most cost-effective method of accessing the deposit, which lies under a sand overburden of about 80 m.

Phase 1 of the project will confirm the grade, diamond prices and recovery processes, including the use of autogenous milling, which is expected to increase diamond liberation. Results from Phase 1 will underpin a study aimed at defining the way forward for mining at Ghaghoo.

Value
Phase 1 will cost an estimated $96-million to implement.

Duration
Gem Diamonds officially opened its new Ghaghoo diamond mine on September 5.

Commercial production will start in the second half of 2014.

Latest Developments
Ghaghoo’s $150/ct has Investec Securities analysts expressing concern about the Botswana mine’s viability in current market conditions.

Gem CEO Clifford Elphick, however, has said that Ghaghoo remains an important future company option but that it is prudent to downsize the operation in the short term to minimise cash consumed by development.

Ghaghoo treated 85 046 t and recovered 24 294 ct in the three months to December 31, 2015.

Key Contracts and Suppliers
Redpath South Africa (incline sand tunnel contract).

On Budget and on Time?
Phase 1 development at Ghaghoo has been achieved on time and within budget. The processing plant is being commissioned. The planned full production of 720 000 t/y of kimberlite for 2015 remains on track.

Contact Details for Project Information
Gem Diamonds Botswana, tel +267 3182 796 or fax +267 3182 795.
Gem Diamonds public and media relations Sherryn Tedder, tel +44 20 3043 0280 or email stedder@gemdiamonds.com.
Redpath South Africa COO Lawrence Schultz, tel +27 11 570 4300, fax +27 11 974 2075 or email Lawrence.schultz@redpathmining.co.za.
 

Edited by Creamer Media Reporter

Comments

Showroom

Flameblock
Flameblock

FlameBlock is a proudly South African company that engineers, manufactures and supplies fire intumescent and retardant products to the fire...

VISIT SHOWROOM 
John Deere (Pty) Ltd
John Deere (Pty) Ltd

In 1958 John Deere Construction made its first introduction to the industry with their model 64 bulldozer.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.094 0.126s - 90pq - 2rq
Subscribe Now