Gamsberg zinc project, South Africa

2nd March 2018

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of Project
Gamsberg zinc project.

Location
Northern Cape, South Africa.

Client
Vedanta Zinc International (VZI) is a grouping of Vedanta Limited’s zinc assets in Southern Africa and Ireland. The grouping comprises Black Mountain Mining and the Gamsberg zinc project, both in South Africa’s Northern Cape province; Skorpion Zinc, in the Karas region of southern Namibia; and Lisheen, in Ireland, which is in advanced orderly closure mode.

Project Description
Gamsberg is being developed on one of the world’s largest known, but as yet undeveloped, zinc deposits.

While Gamsberg's grade is relatively low – between 6% and 6.5% – its current reserve and resource is 214-million tonnes, and the life-of-mine is estimated at 30 years. A substantial portion of the orebody has yet to be drilled to prove additional reserves and resources.

The first phase of the project will comprise an openpit mine, a concentrator and associated infrastructure that includes:
• a tailings dam, a waste rock dump and stockpiles,
• offices and workshops,
• a power transmission line from the Aggeneys substation to Gamsberg,
• a water pipeline,
• an access road from the N14 to Gamsberg,and
• 300 to 350 housing units for accommodation requirements.

The first phase of the project is expected to have a mine life of 13 years, replacing the production lost by the closure of the Lisheen mine and restoring volumes to more than 300 000 t/y.

There is also significant potential for further expansion at the Gamsberg North deposit.

Potentail Job Creation
At the peak of construction, the project is expected to employ about 1 500 people. When operational, Gamsberg will employ between 850 and 900 people.

Value
The capital cost of Phase 1, through a range of innovative adjustments made by the project team to keep Gamsberg's development on track when the zinc price weakened, has been reduced from $600-million to $400-million.

About 80% of the costs for Phase 1 are committed.

Duration
The first blast for Phase 1 took place in July 2015. Phase 1 production, starting in mid-2018, will increase to four-million tonnes of ore and 250 000 t/y of zinc concentrate in a 9- to12-month ramp-up.

Latest Developments
Construction of the concentrator at Gamsberg is under way, with cold commissioning expected in the first quarter of the company’s 2019 financial year, and power and water infrastructure 90% complete. Eventual full production of 250 000 t/y is earmarked.

Seventy per cent of Gamsberg’s prestripping is complete and a 500 000 t ore stockpile is targeted ahead of first feed. Waste stripping is expected to be fully completed by the fourth quarter of the company’s 2019 financial year.

As reported by Mining Weekly in December, Vedanta Zinc International is implementing a digitalisation initiative that will result in a ‘smart ore movement’ system built into Gamsberg to ensure that all available information on the state of the mine, the quality of the ore, the conditions of the processing plant and the value of the output product is made available to the mine management team in real time and presented in a way that allows for minute-by-minute decision-making.

Key Contracts and Suppliers
Aveng Moolmans (bulk mining); ELB Group (concentrator and associated infrastructure); Liviero Civils (tailings dam), Zest WEG Group, including Shaw Controls MV (upgrade of municipal supply station providing water for the mine and zinc concentration plant).

On Budget and on Time?
Yes.

Contact Details for Project Information
Zinc International Manager PR and Corporate Affairs Christo Witbooi, tel + +27 54 983 9225 or email CWitbooi@blackmountain.co.za.
 
 
 
 

Edited by Creamer Media Reporter

Comments

Projects

Showroom

WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 
SBS Tanks
SBS Tanks

SBS® Tanks is a leading provider of innovative water security solutions with offices in Southern Africa, East and West Africa, the USA and an...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.114 0.153s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: