PERTH (miningweekly.com) – The Cobre Panama copper project, being developed by dual-listed First Quantum Minerals, is 72% complete and due for first concentrate production early in 2019.
Project manager Gavin Ashley told delegates at the Latin America Downunder conference, in Perth, that the process plant would be commissioned by the second half of this year, with project construction likely to be completed before the end of the year.
First Quantum in February announced a 15% increase in production capacity at Cobre Panama, with the project now expected to process some 85-million tonnes a year of ore, to deliver 350 000 t/y of copper concentrates.
Ashley noted that the company was targeting the production of 150 000 t of copper in concentrate during 2019, ramping up to between 270 000 t to 300 000 t in 2020.
By 2021, the mine was expected to deliver its targeted 350 000 t/y of copper in concentrate, treating 85-million tonnes of ore a year.
Ashley told delegates that the Cobre Panama project had been designed with a final upgrade figure of 100-million tonnes a year in mind, and in some areas, First Quantum had already invested in the upgrade potential.
He said that the company would assess the debottlenecking and optimisation of Cobre Panama during the ramp-up and operations, to delineate where further capital investment was required to increase production, should the market demand the Cobre Panama product grow.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation