JOHANNESBURG (miningweekly.com) – Despite halting the start of the bankable feasibility study (BFS) for the Moonlight iron-ore project until sufficient funding had been negotiated, triple-listed Ferrum Crescent continued to map out the work planning programme.

During the June quarter, the South Africa-focused iron-ore developer continued to “gear-up” for the start of the BFS, concluding a detailed review of the A$10-million to A$13-million, 18-month study, MD Tom Revy said in an update to shareholders.

A work pathway identified advanced metallurgy, pilot plant construction and final product analysis as the next key components for the BFS.

“This work allows final costing to be made for the mining plan and items such as the pellet plant,” he explained.

The company was now pursuing funding options – in South Africa and internationally – after Oman-based Anvwar Asian Investments (AAI) failed to deliver on a second payment of $500 000 by April 30 under a two-tranche, $1-million funding agreement between the parties.

Ferrum had expected to restart the BFS on receipt of the funding.

“It is unfortunate that AAI has, thus far, not carried out its side of the agreement that was reached in March, but we are continuing to talk to AAI,” Revy said, adding that Ferrum had informed AAI of its default and had not accepted a request for an extension period to complete the financing.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

PGMs and green hydrogen make headlines
PGMs and green hydrogen make headlines
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.17 0.213s - 88pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: