https://www.miningweekly.com

Economics of proposed agreement ‘very attractive’

POSSIBLE TRIBUTE AGREEMENT
The agreement will allow Stellar to mine the Tonguma licence area alongside the company’s own Tongo project and process and sell any diamonds mined from these concessions

POSSIBLE TRIBUTE AGREEMENT The agreement will allow Stellar to mine the Tonguma licence area alongside the company’s own Tongo project and process and sell any diamonds mined from these concessions

Photo by Reuters

14th April 2017

     

Font size: - +

If finalised, a tribute agreement between West Africa-focused diamond development company Stellar Diamonds and diamond mining company Octea Mining will see Stellar simultaneously mine both its wholly owned Tongo project and the adjacent Tonguma project, in eastern Sierra Leone, with the company being the operator of the combined mine.

Stellar announced in February that it had decided against acquiring the Tonguma kimberlite diamond project or its mining licence from Octea.

Instead, the tribute mining agreement that Stellar and Octea intend to enter into will allow Stellar to mine the Tonguma licence area alongside the company’s own Tongo project and process and sell any diamonds mined from these concessions while paying a proportion of the sale proceeds to Octea.

The mine plan detailed in the Tongo-Tonguma preliminary economic assessment (PEA) remains unchanged and demonstrates a financially robust and high margin 21-year life-of-mine (LoM) over an initial inferred diamond resource of 4.5-million carats, with an estimated 3.96-million carats recoverable at a cutoff of 1.18 mm.

The PEA highlights an estimated pretax project net present value (NPR) of $172- million and an internal rate of return (IRR) of 49%, with LoM project revenues of $1.518- million and operating costs of $847-million projected.

There is an estimated operating margin of 50% over the LoM, while first production is expected within 12 months of funding and development starting, increasing to over 200 000 ct/y in the fourth year.

The PEA also points to an expected capital expenditure of $31.8-million in the first two years, including a 15% contingency. However, the Tongo-Tonguma mine modelled in the PEA assumes that the tribute agreement will remain valid and in place for the forecast LoM.

The PEA and competent persons reports also reconognise that there is considerable potential upside from additional high-grade kimberlite dykes on the properties, which are not yet categorised into resource.

“The directors believe the economics of the proposed tribute agreement are very attractive to Stellar; subject to the terms of the tribute agreement remaining in force over the LoM, Stellar has estimated its post-tax NPV arising from the Tongo-Tonguma mine could be about $104-million,” says CE Karl Smithson.

The tribute agreement would be a subcontract arrangement between Octea and Stellar, entered into in the ordinary course of business.

Entering into the tribute agreement is not deemed to constitute a reverse takeover under the Aim rules; however, trading in Stellar’s shares on the Aim was suspended pending completion of a fundraise.

As of February 20, Stellar Diamonds had invested more than $7-million at Tongo, representing about 18p for an existing ordinary share in issue.

Tribute Heads of Terms
In contemplation of the parties entering into a tribute mining agreement, Stellar has agreed to exclusive heads of terms which will see it fund and operate the enlarged mine development and take on responsibility for the processing and marketing of the diamonds recovered.

Further, a 10% share of gross revenues, after the deduction of any government royalties, is payable to Octea on diamond and other minerals recovered and sold, but only after Stellar has recouped an amount equal to its development capital and Octea Mining has received an initial revenue share payment of $5-million.

This one-off payment must be made to Octea five years after mine development starts.

Stellar will also reimburse Octea for certain costs such as an amount equal to the yearly Tonguma mining licence fee.

Certain assets of Tonguma, including the 50 t/h processing plant at Octea’s Koidu mine, will be acquired by Stellar for a nominal amount.

Stellar intends to relocate and upgrade the plant which will then become the processing facility for the combined mining operation.

The final tribute agreement is expected to include a timeframe within which implementation of the mine plan is expected to be completed; however, this timeframe has yet to be negotiated.

The heads of terms of the tribute agreement are nonbinding save for certain clauses, including inter alia and exclusivity provisions.

The exclusivity period extends to April 30.

Entering into the tribute agreement remains subject to inter alia, legal contract, finalisation of legal due diligence work, valid licence opinions being obtained for the Tonguma licence and the acknowledgement of the government of Sierra Leone.

Owing

to the nature of the combined mine plan that is intended to be implemented, any revenue share payments payable to Octea will be for diamond revenues from both the Tongo and Tonguma licences.

The revenue share economics that have been agreed reflect this.

Under the envisaged tribute agreement, Octea will continue to hold the Tonguma mining licence through its subsidiary company Tonguma and Stellar will continue to wholly own its adjacent Tongo licence and subsidiary company Sierra Diamonds.

Stellar Diamonds will also own all infrastructure and capital items procured and used for the mine development on both licences.
Octea Mining has agreed that, for so long as the tribute agreement is in place, it will not sell Tonguma or the Tonguma licence to a third party.

The tribute agreement will, however, include termination clauses whereby the agreement can be terminated by either party for breach of the agreement.

Shareholders should note that, in the event of termination, Stellar Diamonds would have no rights over Tonguma or the Tonguma licence except for any contractual rights accrued.

While negotiations and legal drafting with Octea are at an advanced stage and Stellar has entered into a technical due diligence exercise with a potential strategic investor, there is no guarantee that the company will enter into the tribute agreement or raise the necessary funds to implement the mine plan to discharge Stellar’s obligations under the terms of the tribute agreement.

“We hope to be able to bring the formal agreement and due diligence process to a conclusion in the near future and will continue to engage with potential strategic investors.” states Smithson.

Edited by Tracy Hancock
Creamer Media Contributing Editor

Comments

Latest Multimedia

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
Updated 7 hours ago

Showroom

SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 
Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.182 0.218s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: