Eastplats completes framework agreement with Union Goal

4th September 2018

By: Simone Liedtke

Creamer Media Social Media Editor & Senior Writer

     

Font size: - +

Following the fulfilment of the conditions precedent regarding the Union Goal Offshore Solution framework agreement for the Barplats Zandfontein upper group two (UG2) tailings facility, in South Africa, JSE- and TSX-listed Eastern Platinum (Eastplats) continues the construction phase of the retreatment project.

The project is expected to be completed in the third quarter of the year and will be followed immediately by commissioning.

The conditions precedent included, among other requirements, the securing of the now nonrefundable upfront payment of R42.2-million to Barplats and the signing of the offtake agreement, equipment and chrome plant agreement, an escrow agreement, as well as a loan agreement.

The agreement provides for the construction, mining and processing of the tailings resource, and the subsequent offtake of chrome concentrate from the Barplats Zandfontein UG2 tailings facility.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Latest News

Magazine video image
Magazine round up | 29 March 2024
29th March 2024

Showroom

Showroom image
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 
AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:1.794 1.838s - 90pq - 2rq
Subscribe Now